16027-16029 W CHASE AVE 91343

Certificate Information: 16027-16029 W CHASE AVE 91343

Application / Permit
19016-30000-33510
Plan Check / Job No.
B19WL05852
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERTING (E) GARAGE TO AN ADU PER AB494 AND SB229
Permit Issued
Issued on 9/1/2020
Issuing Office
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 TARIK SAOUD
Corrections Issued 10/28/2019 TARIK SAOUD
Building Plans Picked Up 11/7/2019 APPLICANT
Plan Check Approved 2/20/2020 KAVIAN REFAHI
Issued 9/1/2020 APPLICANT
CofO in Progress 2/9/2021 ARTHUR SARGSYAN
CofO in Progress 2/9/2021 ARTHUR SARGSYAN
CofO Issued 4/24/2021 MICHAEL SMITH
Permit Finaled 4/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/6/2019 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 12/6/2019 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 12/6/2019 HISASHI KOBAYAKAWA
Sewer availability Cleared 12/6/2019 HISASHI KOBAYAKAWA

Contact Information

Contractor Farahani Reza; Lic. No.: 1052392-B 25322 REMESA DRIVE      MISSION VIEJO, CA 92691

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2020 Corrections Issued DAVID SCANTLIN
Pre-Inspection 9/21/2020 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 10/14/2020 Partial Approval MICHEL ABAJAN
Underground Mechanical 10/14/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 10/20/2020 Approved MISAEL ESPARZA
Sewer 10/20/2020 Approved MISAEL ESPARZA
Underground Mechanical 10/20/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 11/6/2020 Corrections Issued ARTHUR SARGSYAN
ELECTRICAL-Rough 11/6/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 11/6/2020 Approved ARTHUR SARGSYAN
Insulation 11/13/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 11/23/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 11/23/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/25/2021 Approved ARTHUR SARGSYAN
Final 1/25/2021 Corrections Issued ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/25/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 1/25/2021 Approved ARTHUR SARGSYAN
Final 1/28/2021 OK to Issue CofO ARTHUR SARGSYAN