2238 S LINNINGTON AVE 90064
Certificate Information: 2238 S LINNINGTON AVE 90064
- Application / Permit
- 19016-30000-33364
- Plan Check / Job No.
- B19WL05831
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE/LAUNDRY TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofO Issued on 8/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | TARIK SAOUD |
| Corrections Issued | 10/28/2019 | TARIK SAOUD |
| Applicant returned to address corrections | 8/14/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 9/3/2020 | JASON JANGADA |
| Plan Check Approved | 9/23/2020 | PARISA ZAHABI |
| Issued | 9/30/2020 | APPLICANT |
| Building Plans Picked Up | 10/6/2020 | APPLICANT |
| CofO in Progress | 7/11/2022 | STEPHANIE SWANSON |
| CofO Issued | 8/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/22/2020 | RIDWAN HARDY |
| Address approval | Cleared | 4/24/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/24/2020 | DINAH GARIN |
| Sewer availability | Cleared | 4/24/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 6/26/2020 | MARTIN FRAGOSO |
| Grading Pre-Inspection | Cleared | 7/14/2020 | KIRK LINKLATER |
Contact Information
| Contractor | A K Pro Construction Corp; Lic. No.: 895106-B | 1840 W 220TH STREET SUITE 370 TORRANCE, CA 90501 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/15/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/15/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/17/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 1/8/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/23/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 2/23/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/23/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 2/23/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/26/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 3/2/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 3/2/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 3/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 3/22/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 3/30/2021 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/5/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 4/7/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 4/13/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 5/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 4/20/2022 | Corrections Issued | BRENDAN LOONEY |
| Service/Power Release | 4/20/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 4/22/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 4/22/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 4/22/2022 | Corrections Issued | BRENDAN LOONEY |
| Service/Power Release | 4/22/2022 | Approved | BRENDAN LOONEY |
| Final | 5/10/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 5/10/2022 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Final | 5/10/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 5/10/2022 | Approved | BRENDAN LOONEY |
| Final | 7/11/2022 | OK to Issue CofO | STEPHANIE SWANSON |
| HVAC-Final | 7/11/2022 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 7/11/2022 | Partial Inspection | HERBERT GIRON |