- Work Description
- CONVERT (E) 2-CAR GARAGE INTO AN ADU PER AB 494 AND SB229. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 11/14/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | KAVIAN REFAHI |
| Corrections Issued | 10/18/2019 | KAVIAN REFAHI |
| Building Plans Picked Up | 10/21/2019 | APPLICANT |
| Plan Check Approved | 11/12/2019 | ALFREDO JARA |
| Issued | 11/14/2019 | LADBS |
| CofO in Progress | 7/8/2020 | DAVID CHAN |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
| CofO Issued | 11/13/2020 | DEROLD HAUFF |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/24/2019 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2019 | KATHLEEN HUGHEY |
| Roof/Waste drainage to street | Cleared | 10/24/2019 | DINAH GARIN |
| Sewer availability | Cleared | 10/24/2019 | DINAH GARIN |
| CPC | Cleared | 11/5/2019 | JONATHAN KAPLAN |
| HPOZ | Cleared | 11/5/2019 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 11/5/2019 | JONATHAN KAPLAN |
| Miscellaneous | Cleared | 11/5/2019 | JONATHAN KAPLAN |
Contact Information
| Contractor | Sklar Construction; Lic. No.: 1034994-B | 1474 S CREST DRIVE LOS ANGELES, CA 90035 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/27/2019 | Corrections Issued | ELMER BLAND |
| PLUMBING-Rough | 2/11/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2020 | Partial Approval | DAVID CHAN |
| ELECTRICAL-Rough | 3/4/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 3/4/2020 | Not Ready for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 3/10/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 3/10/2020 | Approved | DAVID CHAN |
| Insulation | 3/23/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 3/23/2020 | Approved | DAVID CHAN |
| Wood Frame | 3/23/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 3/27/2020 | Approved | THOMAS LOGRASSO |
| Gas Test | 3/27/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/27/2020 | Approved | THOMAS LOGRASSO |
| Shower Pan | 3/27/2020 | Approved | THOMAS LOGRASSO |
| Final | 5/13/2020 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Final | 5/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/13/2020 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 5/13/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 5/15/2020 | Not Ready for Inspection | RUBEN SALAS |
| Final | 5/18/2020 | Conditional Approval | DAVID CHAN |
| METHANE-Final | 5/18/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2020 | SGSOV Approved | DAVID CHAN |
| Smoke Detectors | 5/18/2020 | Approved | DAVID CHAN |
| Final | 7/6/2020 | OK to Issue CofO | DAVID CHAN |