1428 S CARMONA AVE 90019

Certificate Information: 1428 S CARMONA AVE 90019

Application / Permit
19016-30000-32966
Plan Check / Job No.
B19WL05762
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (e) detached garage to ADU per AB 494 & SB 229. All work per IB/P/BC 2017-004 wood frame prescriptive provision.
Permit Issued
Issued on 5/15/2020
Issuing Office
Current Status
CofO Issued on 3/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 10/18/2019 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 11/18/2019 APPLICANT
Plan Check Approved 1/2/2020 VLADIMIR ARUTYUNYAN
Issued 5/15/2020 APPLICANT
CofO in Progress 2/28/2024 STUART CHAPMAN
Permit Finaled 3/5/2024 DEROLD HAUFF
CofO Issued 3/5/2024 DEROLD HAUFF
Permit Finaled 3/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/16/2019 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 12/16/2019 ANTHONY MAINEZ
Sewer availability Cleared 12/16/2019 ANTHONY MAINEZ
Construction near power lines Cleared 12/21/2019 RIDWAN HARDY
Hydrant and Access approval Cleared 12/26/2019 JEREMY CARTER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/6/2023 Approved MICHAEL LEWIS
Sewer 3/10/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 3/14/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 5/9/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 5/12/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 5/24/2023 Approved JOSE AVILA
METHANE-Barrier 5/24/2023 Approved JOSE AVILA
METHANE-Subgrade 5/24/2023 Approved JOSE AVILA
ELECTRICAL-Rough 5/31/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/31/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 6/7/2023 Approved JOSE AVILA
ELECTRICAL-Rough 6/7/2023 Approved JOSE AVILA
Green Building Rough 6/7/2023 Approved JOSE AVILA
HVAC-Rough 6/7/2023 Approved JOSE AVILA
Insulation 6/7/2023 Partial Approval JOSE AVILA
METHANE-Rough 6/7/2023 Approved JOSE AVILA
Drywall Nailing 6/22/2023 Approved LILIANA PORTILLO
Final 9/6/2023 No Access for Inspection JOSE AVILA
ELECTRICAL-Final 9/11/2023 Corrections Issued JOSE AVILA
Final 9/18/2023 Corrections Issued JOSE AVILA
Green Building Final 9/18/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 9/18/2023 Approved JOSE AVILA
Final 11/1/2023 Corrections Issued JOSE AVILA
Final 1/4/2024 Not Ready for Inspection RONNIE MINDANAO
Final 2/28/2024 OK to Issue CofO STUART CHAPMAN