1428 S CARMONA AVE 90019
Certificate Information: 1428 S CARMONA AVE 90019
- Application / Permit
- 19016-30000-32966
- Plan Check / Job No.
- B19WL05762
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (e) detached garage to ADU per AB 494 & SB 229. All work per IB/P/BC 2017-004 wood frame prescriptive provision.
- Permit Issued
- Issued on 5/15/2020
- Issuing Office
- Current Status
- CofO Issued on 3/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/18/2019 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 11/18/2019 | APPLICANT |
| Plan Check Approved | 1/2/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 5/15/2020 | APPLICANT |
| CofO in Progress | 2/28/2024 | STUART CHAPMAN |
| Permit Finaled | 3/5/2024 | DEROLD HAUFF |
| CofO Issued | 3/5/2024 | DEROLD HAUFF |
| Permit Finaled | 3/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2019 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/16/2019 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 12/21/2019 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 12/26/2019 | JEREMY CARTER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/6/2023 | Approved | MICHAEL LEWIS |
| Sewer | 3/10/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 3/14/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/12/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/24/2023 | Approved | JOSE AVILA |
| METHANE-Barrier | 5/24/2023 | Approved | JOSE AVILA |
| METHANE-Subgrade | 5/24/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 5/31/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/31/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/7/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 6/7/2023 | Approved | JOSE AVILA |
| Green Building Rough | 6/7/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 6/7/2023 | Approved | JOSE AVILA |
| Insulation | 6/7/2023 | Partial Approval | JOSE AVILA |
| METHANE-Rough | 6/7/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 6/22/2023 | Approved | LILIANA PORTILLO |
| Final | 9/6/2023 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 9/11/2023 | Corrections Issued | JOSE AVILA |
| Final | 9/18/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 9/18/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 9/18/2023 | Approved | JOSE AVILA |
| Final | 11/1/2023 | Corrections Issued | JOSE AVILA |
| Final | 1/4/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 2/28/2024 | OK to Issue CofO | STUART CHAPMAN |