4756 S MCCONNELL AVE 90066

Certificate Information: 4756 S MCCONNELL AVE 90066

Application / Permit
19016-30000-31653
Plan Check / Job No.
B19WL05575
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, REMOVE & REPLACE (E) ATTACHED CARPORT, AND NEW GROUND FLOOR ADDITION FOR THE ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/21/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 SERGIO SILVA
Corrections Issued 11/7/2019 SERGIO SILVA
Quality Review Completed 11/14/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/29/2020 SERGIO SILVA
Plan Check Approved 3/16/2020 SERGIO SILVA
Issued 5/21/2020 LADBS
Building Plans Picked Up 5/26/2020 APPLICANT
CofO in Progress 4/19/2021 ENRIQUE MIRELES
CofO Issued 9/7/2021 RONALD MYRICK
Permit Finaled 9/7/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/11/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 12/11/2019 JAMES MORALEZ
Hydrant and Access approval Cleared 12/11/2019 GEORGE SUCHAND
Sewer availability Cleared 12/11/2019 JAMES MORALEZ
Street width determination Cleared 12/11/2019 JAMES MORALEZ
Construction near power lines Cleared 2/19/2020 ERNEST FRESQUEZ
Low Impact Development Cleared 2/27/2020 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 2/27/2020 EMIL KYUPELYAN
Green Code Cleared 3/10/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Orland,, James Curtiss; Lic. No.: C22024 660 18TH ST      MANHATTAN BEACH, CA 90266

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2020 Partial Approval JOHNNY MIRANDA
METHANE-Barrier 6/3/2020 Approved JOHNNY MIRANDA
METHANE-Subgrade 6/3/2020 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/11/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 6/11/2020 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/16/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 7/13/2020 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 7/13/2020 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 7/13/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 7/13/2020 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 7/13/2020 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 8/19/2020 Conditional Approval CRAIG DAVIS
ELECTRICAL-Rough 8/19/2020 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Partial Approval CRAIG DAVIS
HVAC-Rough 8/19/2020 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/19/2020 Corrections Issued CRAIG DAVIS
Wood Frame 8/19/2020 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 9/2/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 9/2/2020 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 9/2/2020 Approved JOHNNY MIRANDA
HVAC-Rough 9/2/2020 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 9/2/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 9/2/2020 Corrections Issued JOHNNY MIRANDA
Wood Frame 9/2/2020 Approved JOHNNY MIRANDA
Insulation 9/10/2020 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 9/14/2020 Approved JOHNNY MIRANDA
Insulation 9/14/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 9/14/2020 Approved JOHNNY MIRANDA
Drywall Nailing 9/18/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/14/2020 Approved JOHNNY MIRANDA
Final 3/12/2021 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 3/12/2021 Approved DAVID HEINE
Green Building Final 3/12/2021 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Not Ready DAVID HEINE
Smoke Detectors 3/12/2021 Approved DAVID HEINE
Final 3/23/2021 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Not Ready JUAN VALENZUELA
Final 4/9/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved JOHNNY MIRANDA
Final 4/19/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 4/19/2021 Approved ENRIQUE MIRELES
Special/Order Compliance 5/11/2021 Corrections Issued JOHNNY MIRANDA