4756 S MCCONNELL AVE 90066
Certificate Information: 4756 S MCCONNELL AVE 90066
- Application / Permit
- 19016-30000-31653
- Plan Check / Job No.
- B19WL05575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF (E) GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, REMOVE & REPLACE (E) ATTACHED CARPORT, AND NEW GROUND FLOOR ADDITION FOR THE ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 5/21/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | SERGIO SILVA |
| Corrections Issued | 11/7/2019 | SERGIO SILVA |
| Quality Review Completed | 11/14/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/29/2020 | SERGIO SILVA |
| Plan Check Approved | 3/16/2020 | SERGIO SILVA |
| Issued | 5/21/2020 | LADBS |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| CofO in Progress | 4/19/2021 | ENRIQUE MIRELES |
| CofO Issued | 9/7/2021 | RONALD MYRICK |
| Permit Finaled | 9/7/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2019 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 12/11/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 12/11/2019 | JAMES MORALEZ |
| Street width determination | Cleared | 12/11/2019 | JAMES MORALEZ |
| Construction near power lines | Cleared | 2/19/2020 | ERNEST FRESQUEZ |
| Low Impact Development | Cleared | 2/27/2020 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 2/27/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 3/10/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Orland,, James Curtiss; Lic. No.: C22024 | 660 18TH ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2020 | Partial Approval | JOHNNY MIRANDA |
| METHANE-Barrier | 6/3/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 6/3/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/11/2020 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/16/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/13/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 7/13/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 7/13/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/13/2020 | Corrections Issued | JOHNNY MIRANDA |
| Underground Mechanical | 7/13/2020 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 8/19/2020 | Conditional Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 8/19/2020 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2020 | Partial Approval | CRAIG DAVIS |
| HVAC-Rough | 8/19/2020 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 8/19/2020 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 8/19/2020 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 9/2/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/2/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 9/2/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 9/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/2/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/2/2020 | Corrections Issued | JOHNNY MIRANDA |
| Wood Frame | 9/2/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 9/10/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 9/14/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 9/14/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/14/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 9/18/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/14/2020 | Approved | JOHNNY MIRANDA |
| Final | 3/12/2021 | Corrections Issued | DAVID HEINE |
| Footing/Foundation/Slab | 3/12/2021 | Approved | DAVID HEINE |
| Green Building Final | 3/12/2021 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Not Ready | DAVID HEINE |
| Smoke Detectors | 3/12/2021 | Approved | DAVID HEINE |
| Final | 3/23/2021 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 3/23/2021 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 4/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 4/19/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 4/19/2021 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 5/11/2021 | Corrections Issued | JOHNNY MIRANDA |