9748 N HILLHAVEN AVE 91042
Certificate Information: 9748 N HILLHAVEN AVE 91042
- Application / Permit
- 19016-30000-31110
- Plan Check / Job No.
- B19WL05513
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN (E) STORAGE INTO ACCESSORY DWELLING UNIT. PER AB 494 & SB 229
- Permit Issued
- Issued on 2/19/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2019 | ALFREDO JARA |
| Corrections Issued | 10/11/2019 | ALFREDO JARA |
| Building Plans Picked Up | 10/21/2019 | APPLICANT |
| Plan Check Approved | 2/19/2020 | ALFREDO JARA |
| Issued | 2/19/2020 | LADBS |
| CofO in Progress | 3/4/2021 | BEAU COLLINS |
| Permit Finaled | 3/8/2023 | DANIEL ORRANTE |
| CofO Issued | 3/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2019 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/5/2019 | DINAH GARIN |
| Sewer availability | Cleared | 12/5/2019 | DINAH GARIN |
| Specific Plan | Cleared | 2/13/2020 | PEGGY MALONE-BROWN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/18/2020 | Approved | BEAU COLLINS |
| PLUMBING-Rough | 7/6/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 7/6/2020 | Partial Inspection | PIERRE VEGA |
| PLUMBING-Rough | 10/27/2020 | Partial Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 11/9/2020 | Approved | BEAU COLLINS |
| PLUMBING-Rough | 11/9/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 12/7/2020 | Not Ready for Inspection | BEAU COLLINS |
| ELECTRICAL-Rough | 12/7/2020 | Partial Approval | BEAU COLLINS |
| Insulation | 12/14/2020 | Approved | BEAU COLLINS |
| ELECTRICAL-Final | 1/29/2021 | Corrections Issued | BEAU COLLINS |
| ELECTRICAL-Rough | 2/2/2021 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 2/2/2021 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 2/17/2021 | Approved | BEAU COLLINS |
| Drywall Nailing | 2/17/2021 | Approved | BEAU COLLINS |
| Final | 2/17/2021 | Corrections Issued | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 2/17/2021 | SGSOV Approved | BEAU COLLINS |
| Smoke Detectors | 2/17/2021 | Approved | BEAU COLLINS |
| Final | 3/3/2021 | OK to Issue CofO | BEAU COLLINS |