2237 W LAVERNA AVE 90041

Certificate Information: 2237 W LAVERNA AVE 90041

Application / Permit
19016-30000-30587
Plan Check / Job No.
B19WL05438
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
conversion of existing garage to ADU with addition per AB494 and SB229.
Permit Issued
Issued on 12/22/2020
Issuing Office
Current Status
CofO Corrected on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 MANUEL GARCIA
Corrections Issued 10/8/2019 MANUEL GARCIA
Applicant returned to address corrections 12/10/2019 KAVIAN REFAHI
Plan Check Approved 1/9/2020 TARIK SAOUD
Issued 12/22/2020 APPLICANT
Building Plans Picked Up 12/29/2020 APPLICANT
CofO in Progress 10/20/2022 CRAIG VAUGHAN
CofO Issued-Status Void 11/12/2022 DEROLD HAUFF
Permit Finaled-Status Void 11/12/2022 DEROLD HAUFF
Re-Activate Permit 11/14/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Corrected 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/17/2019 JOSE CRUZ RODRIGUEZ
Frnt yard landscape/Water mgmt Cleared 10/17/2019 TREVOR MARTIN
Highway dedication Cleared 10/17/2019 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/17/2019 JOSE CRUZ RODRIGUEZ
Grading Pre-Inspection Cleared 12/10/2019 MANUEL GARCIA
Eng Process Fee Ord 176,300 Cleared 1/9/2020 ANTHONY MAINEZ
Sewer availability Cleared 1/9/2020 ANTHONY MAINEZ

Contact Information

Architect Belak-Berger,, Charles Peter; Lic. No.: C13657 521 W. ROSECRANS AVE.      GARDENA, CA 902481514
Contractor Eagle Rock Restoration; Lic. No.: 1025285-B 5464 WAMEDA AVE      LOS ANGELES, CA 90041

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/5/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 1/7/2021 Corrections Issued CRAIG VAUGHAN
METHANE-Barrier 1/7/2021 Approved CRAIG VAUGHAN
METHANE-Subgrade 1/7/2021 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 1/14/2021 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 1/15/2021 Approved CRAIG VAUGHAN
Insulation 2/22/2021 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 3/8/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/8/2021 Corrections Issued CRAIG VAUGHAN
Green Building Rough 3/8/2021 Approved CRAIG VAUGHAN
METHANE-Rough 3/8/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/8/2021 Partial Approval CRAIG VAUGHAN
Underground Mechanical 3/8/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 4/5/2021 Approved CRAIG VAUGHAN
HVAC-Rough 4/5/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/5/2021 Approved CRAIG VAUGHAN
Wood Frame 4/5/2021 Corrections Issued CRAIG VAUGHAN
Deputy Drilled-In Anchors 4/7/2021 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/14/2021 Approved HAMIK HARTOUNIAN
Insulation 4/19/2021 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 4/19/2021 Partial Approval STEPHANIE SWANSON
Pre-Inspection 4/19/2021 Partial Inspection JAVIER RAMOS JR
Insulation 5/13/2021 Approved CRAIG VAUGHAN
Drywall Nailing 5/24/2021 Approved RICHARD STEINBACH
Interior/Exterior Lathing 5/24/2021 Approved RICHARD STEINBACH
Shower Pan 5/24/2021 Approved RICHARD STEINBACH
Final 7/30/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 7/30/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/30/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/30/2021 Approved CRAIG VAUGHAN
Final 9/16/2021 Corrections Issued CRAIG VAUGHAN
Final 10/19/2022 OK to Issue CofO CRAIG VAUGHAN