1305 N VERMONT AVE 90027
Certificate Information: 1305 N VERMONT AVE 90027
- Application / Permit
- 19016-30000-30043
- Plan Check / Job No.
- B19WL05344
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Tenant improvement and exterior renovation to (E) restaurant. No change in use/No change in parking.
- Permit Issued
- Issued on 9/24/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/22/2021
Permit Application Status History
| Submitted | 9/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | ALFREDO JARA |
| Corrections Issued | 10/7/2019 | ALFREDO JARA |
| Quality Review Completed | 10/18/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/22/2020 | ALFREDO JARA |
| Applicant returned to address corrections | 6/29/2020 | ALFREDO JARA |
| Disabled Access Plans Picked Up | 7/30/2020 | APPLICANT |
| Plan Check Approved | 9/23/2020 | ALFREDO JARA |
| Issued | 9/24/2020 | APPLICANT |
| Building Plans Picked Up | 10/29/2020 | APPLICANT |
| Permit Finaled | 4/16/2021 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/29/2019 | JASON HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 11/5/2019 | APEKSHYA BAJRACHARYA |
| DAS Clearance | Cleared | 3/4/2020 | SOMKIAT SUPANYACHOTSKUL |
| Food Service Establishment | Cleared | 9/18/2020 | RAMESHBHAIR PATEL |
| Food establishment approval | Cleared | 9/23/2020 | LACDHS APPROVED |
Contact Information
| Architect | Dodson,, John S; Lic. No.: C27716 | 1330 OLYMPIC BLVD SANTA MONICA, CA 90404 |
| Contractor | Clockwork Construction Inc; Lic. No.: 1042273-B | 5656 CORPORATE AVE STE 200 CYPRESS, CA 90630 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2020 | Approved | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 10/1/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Wood Frame | 10/13/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Approved | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 10/22/2020 | Approved | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 11/4/2020 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 11/4/2020 | Approved | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 11/23/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 12/3/2020 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 12/7/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 12/9/2020 | Approved | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 12/15/2020 | Partial Approval | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 1/28/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Wood Frame | 1/28/2021 | Approved | RUSSELL BONVOULOIR |
| Special/Order Compliance | 3/23/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 4/13/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 4/13/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 4/16/2021 | Permit Finaled | RUSSELL BONVOULOIR |