7428 N CALDUS AVE 91406
Certificate Information: 7428 N CALDUS AVE 91406
- Application / Permit
- 19016-30000-28950
- Plan Check / Job No.
- B19WL05158
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) det. garage to an accessory dwelling unit (ADU) per AB 494 and SB 229.
- Permit Issued
- Issued on 1/21/2020
- Issuing Office
- Valley
- Current Status
- Issued on 11/27/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | REZA HAGHIGHAT |
| Corrections Issued | 9/19/2019 | REZA HAGHIGHAT |
| Building Plans Picked Up | 9/24/2019 | APPLICANT |
| Plan Check Approved | 1/10/2020 | KAVIAN REFAHI |
| Issued | 1/21/2020 | LADBS |
| CofO in Progress | 7/6/2020 | DANIEL DREW |
| No Progress | 11/27/2020 | MICHAEL TEMPLE |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 10/25/2019 | JOHN CONNEALLY |
| Sewer availability | Cleared | 10/25/2019 | THOMAS LANG |
| Construction near power lines | Cleared | 12/16/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/13/2020 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/26/2020 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/26/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 2/26/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Sewer | 2/26/2020 | Partial Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/6/2020 | Partial Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/6/2020 | Approved | JACK KARGODORIAN |
| Gas Test | 3/6/2020 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/6/2020 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/13/2020 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 3/19/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/19/2020 | Approved | TROY SANDERS |
| Shower Pan | 3/19/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 6/29/2020 | Approved | DANIEL DREW |
| Final | 6/29/2020 | OK to Issue CofO | DANIEL DREW |
| HVAC-Final | 6/29/2020 | Approved | DANIEL DREW |
| PLUMBING-Final | 6/29/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 6/29/2020 | SGSOV Approved | DANIEL DREW |
| Service/Power Release | 6/29/2020 | Approved | DANIEL DREW |
| Smoke Detectors | 6/29/2020 | Approved | DANIEL DREW |