2351 S PROSSER AVE 90064
Certificate Information: 2351 S PROSSER AVE 90064
- Application / Permit
- 19016-30000-27283
- Plan Check / Job No.
- B19WL04892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) garage to an ADU per Ordinance. Addition in the front.
- Permit Issued
- Issued on 4/28/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2019 | TARIK SAOUD |
| Corrections Issued | 9/4/2019 | TARIK SAOUD |
| Building Plans Picked Up | 9/5/2019 | APPLICANT |
| Plan Check Approved | 3/15/2021 | MANUEL GARCIA |
| Issued | 4/28/2021 | APPLICANT |
| CofO in Progress | 1/17/2023 | STEPHANIE SWANSON |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
| CofO Issued | 1/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/5/2019 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2019 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 9/5/2019 | DENNIS BRAGIN |
| Sewer availability | Cleared | 9/5/2019 | DENNIS BRAGIN |
| Grading Pre-Inspection | Cleared | 1/9/2020 | KIRK LINKLATER |
Contact Information
| Contractor | Malekmanesh Kamyar; Lic. No.: 604814-B | 4162 WOODCLIFF ROAD SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 6/17/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/3/2021 | Corrections Issued | BRENDAN LOONEY |
| Sewer | 12/3/2021 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/7/2021 | Partial Approval | BRENDAN LOONEY |
| Sewer | 12/7/2021 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 2/10/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 2/10/2022 | Corrections Issued | BRENDAN LOONEY |
| Shower Pan | 2/10/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 3/4/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/18/2022 | Corrections Issued | BRENDAN LOONEY |
| METHANE-Rough | 5/18/2022 | Approved | BRENDAN LOONEY |
| Wood Frame | 5/27/2022 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/21/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/21/2022 | Approved | JOHN KIDWELL |
| Insulation | 7/1/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 7/18/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/8/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 1/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 1/11/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 1/11/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 1/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Service/Power Release | 1/11/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 1/11/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 1/17/2023 | Approved | STEPHANIE SWANSON |
| Final | 1/17/2023 | OK to Issue CofO | STEPHANIE SWANSON |
| PLUMBING-Final | 1/17/2023 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 1/17/2023 | Approved | STEPHANIE SWANSON |