6709 N COSTELLO AVE 91405
Certificate Information: 6709 N COSTELLO AVE 91405
- Application / Permit
- 19016-30000-23031
- Plan Check / Job No.
- B19WL04218
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 1-STORY TYPE VB 2-CAR GARAGE WTIH ATTACHED STORAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 12/31/2020
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2019 | SERGIO SILVA |
| Green Plans Picked Up | 8/28/2019 | APPLICANT |
| Corrections Issued | 8/30/2019 | SERGIO SILVA |
| Quality Review Completed | 9/6/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 9/9/2019 | APPLICANT |
| Applicant returned to address corrections | 11/8/2019 | SERGIO SILVA |
| Plan Check Approved | 11/12/2019 | SERGIO SILVA |
| Issued | 12/31/2020 | APPLICANT |
| CofO in Progress | 3/1/2022 | RICHARD DOCKUS |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2019 | DINAH GARIN |
| CPC | Cleared | 10/2/2019 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2019 | DINAH GARIN |
| Permit | Cleared | 10/2/2019 | DINAH GARIN |
| Sewer availability | Cleared | 10/2/2019 | DINAH GARIN |
| Low Impact Development | Cleared | 10/4/2019 | RYAN HUDSON |
| Hydrant and Access approval | Cleared | 10/24/2019 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 10/24/2019 | DINAH GARIN |
| Green Code | Cleared | 11/6/2019 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/20/2021 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/28/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 8/19/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 8/27/2021 | Approved | RICHARD DOCKUS |
| Gas Test | 8/27/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 8/27/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 8/27/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/31/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/31/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/31/2021 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 8/31/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 9/3/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/3/2021 | Approved | AMY COLIN |
| Drywall Nailing | 9/8/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 9/8/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/13/2021 | Approved | AMY COLIN |
| Final | 11/9/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 11/9/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 11/9/2021 | Approved | RICHARD DOCKUS |
| Final | 2/16/2022 | Corrections Issued | MICHAEL TEMPLE |
| Final | 2/28/2022 | OK to Issue CofO | RICHARD DOCKUS |