4432 S HARDING AVE 90066
Certificate Information: 4432 S HARDING AVE 90066
- Application / Permit
- 19016-30000-19574
- Plan Check / Job No.
- B19WL03617
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) garage to accessory dwelling unit per CA 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2019 | ALFREDO JARA |
| Corrections Issued | 7/5/2019 | ALFREDO JARA |
| Applicant returned to address corrections | 6/8/2020 | JESSE JIMENEZ |
| Plan Check Approved | 8/24/2020 | ADAM HEGAZI |
| Building Plans Picked Up | 8/25/2020 | APPLICANT |
| Issued | 6/22/2021 | APPLICANT |
| CofO in Progress | 8/15/2025 | RUBEN RIVAS |
| Permit Finaled | 8/19/2025 | RICHARD STEINBACH |
| CofO Issued | 8/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/27/2020 | DINAH GARIN |
| Sewer availability | Cleared | 5/27/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 1/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/19/2024 | Corrections Issued | MICHAEL ALLEN |
| Special/Order Compliance | 11/19/2024 | Partial Inspection | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 1/3/2025 | Approved | MICHAEL ALLEN |
| Deputy Drilled-In Anchors | 1/14/2025 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/3/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 3/3/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 3/3/2025 | Corrections Issued | HERBERT GIRON |
| Rough-Elec/Plmb/HVAC | 3/27/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Special/Order Compliance | 3/27/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Wood Frame | 3/27/2025 | Not Ready for Inspection | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/3/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/3/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/3/2025 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/3/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/7/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 4/7/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 4/10/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/11/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 4/11/2025 | Partial Approval | RUBEN RIVAS |
| Footing/Foundation/Slab | 4/11/2025 | Partial Approval | RUBEN RIVAS |
| HVAC-Rough | 4/11/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 4/11/2025 | Partial Approval | RUBEN RIVAS |
| Reinforced Concrete Frame | 4/11/2025 | Partial Approval | RUBEN RIVAS |
| Rough-Elec/Plmb/HVAC | 4/11/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 4/16/2025 | Approved | RUBEN RIVAS |
| Rough-Elec/Plmb/HVAC | 4/16/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 4/21/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 7/3/2025 | Approved | BOBBY KEY |
| Final | 7/3/2025 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/3/2025 | SGSOV Not Required | BOBBY KEY |
| Smoke Detectors | 7/3/2025 | Approved | BOBBY KEY |
| Final | 8/7/2025 | OK to Issue CofO | RUBEN RIVAS |