4432 S HARDING AVE 90066

Certificate Information: 4432 S HARDING AVE 90066

Application / Permit
19016-30000-19574
Plan Check / Job No.
B19WL03617
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) garage to accessory dwelling unit per CA 65852.2(e)(1)(A)
Permit Issued
Issued on 6/22/2021
Issuing Office
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2019 APPLICANT
Assigned to Plan Check Engineer 7/2/2019 ALFREDO JARA
Corrections Issued 7/5/2019 ALFREDO JARA
Applicant returned to address corrections 6/8/2020 JESSE JIMENEZ
Plan Check Approved 8/24/2020 ADAM HEGAZI
Building Plans Picked Up 8/25/2020 APPLICANT
Issued 6/22/2021 APPLICANT
CofO in Progress 8/15/2025 RUBEN RIVAS
Permit Finaled 8/19/2025 RICHARD STEINBACH
CofO Issued 8/19/2025 RICHARD STEINBACH
Permit Finaled 8/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/27/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 5/27/2020 DINAH GARIN
Sewer availability Cleared 5/27/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/28/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2023 Not Ready for Inspection JESUS RODRIGUEZ
Pre-Inspection 1/19/2023 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 11/19/2024 Corrections Issued MICHAEL ALLEN
Special/Order Compliance 11/19/2024 Partial Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 1/3/2025 Approved MICHAEL ALLEN
Deputy Drilled-In Anchors 1/14/2025 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 3/3/2025 Corrections Issued HERBERT GIRON
HVAC-Rough 3/3/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 3/3/2025 Corrections Issued HERBERT GIRON
Rough-Elec/Plmb/HVAC 3/27/2025 Not Ready for Inspection RUBEN RIVAS
Special/Order Compliance 3/27/2025 Partial Inspection TEMISTOCLES CAAL
Wood Frame 3/27/2025 Not Ready for Inspection RUBEN RIVAS
BUILDING-Rough-Frame 4/3/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/3/2025 Approved ARAM AVEDISIAN
HVAC-Rough 4/3/2025 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/3/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 4/7/2025 Approved RUBEN RIVAS
PLUMBING-Rough 4/7/2025 Corrections Issued RUBEN RIVAS
PLUMBING-Rough 4/10/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 4/11/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 4/11/2025 Partial Approval RUBEN RIVAS
Footing/Foundation/Slab 4/11/2025 Partial Approval RUBEN RIVAS
HVAC-Rough 4/11/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 4/11/2025 Partial Approval RUBEN RIVAS
Reinforced Concrete Frame 4/11/2025 Partial Approval RUBEN RIVAS
Rough-Elec/Plmb/HVAC 4/11/2025 Partial Approval RUBEN RIVAS
Insulation 4/16/2025 Approved RUBEN RIVAS
Rough-Elec/Plmb/HVAC 4/16/2025 Approved RUBEN RIVAS
Drywall Nailing 4/21/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 4/21/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 7/3/2025 Approved BOBBY KEY
Final 7/3/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Not Required BOBBY KEY
Smoke Detectors 7/3/2025 Approved BOBBY KEY
Final 8/7/2025 OK to Issue CofO RUBEN RIVAS