7022 S RINDGE AVE 90293

Certificate Information: 7022 S RINDGE AVE 90293

Application / Permit
19016-30000-18976
Plan Check / Job No.
B19WL03511
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
(N) ATTACHED OPEN FRONT DECK TO (E) SFD
Permit Issued
Issued on 2/10/2020
Issuing Office
Metro
Current Status
Issued on 2/10/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/21/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 RACHEL BEYENE
Corrections Issued 7/29/2019 RACHEL BEYENE
Quality Review Completed 7/30/2019 QUAN NGHIEM
Building Plans Picked Up 8/1/2019 APPLICANT
Applicant returned to address corrections 11/21/2019 RACHEL BEYENE
Applicant returned to address corrections 12/12/2019 RACHEL BEYENE
Plan Check Approved 2/10/2020 RAHEL BEYENE
Issued 2/10/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/21/2019 ELENA LOPEZ
Frnt yard landscape/Water mgmt Cleared 11/21/2019 TERRI OSBORNE
Low Impact Development Cleared 11/21/2019 JORGE MEJIA LEMUS
Coastal Zone Cleared 12/20/2019 NOAH MCCOY
Encroachment in public way Cleared 1/15/2020 ANTHONY MAINEZ
GPI Written Notices Cleared 2/10/2020 RAHEL BEYENE
Grading Pre-Inspection Cleared 2/10/2020 RAHEL BEYENE

Contact Information

Contractor Lahave Builders Llc; Lic. No.: 1041232-B 7840 WS 81ST STREET      PLAYA DEL REY, CA 90293
Engineer Azarmy,, Cyrus; Lic. No.: L9404 20206 ARCHWOOD ST      WINNETKA, CA 91306
Engineer Howard,, John Edward; Lic. No.: S2953 2193 W GRAMERCY DR      GREEN VALLEY, AZ 85622

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2020 Partial Approval JUAN VALENZUELA
Pre-Inspection 3/11/2020 Partial Inspection JUAN VALENZUELA
METHANE-Rough 3/20/2020 Partial Approval JUAN VALENZUELA
Pre-Inspection 3/25/2020 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 3/27/2020 Approved JUAN VALENZUELA
Wood Frame 4/2/2020 Approved JUAN VALENZUELA
Final 4/15/2020 Conditional Approval JUAN VALENZUELA
METHANE-Final 4/15/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 4/15/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 4/15/2020 Approved JUAN VALENZUELA
Special/Order Compliance 1/28/2021 Approved JOHNNY MIRANDA