8815 W PICO BLVD 90035

Certificate Information: 8815 W PICO BLVD 90035

Application / Permit
19016-30000-18556
Plan Check / Job No.
B19WL03435
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
Change of use portion of building from retail to medical office.
Permit Issued
Issued on 10/11/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2019 APPLICANT
Disabled Access Plans Picked Up 7/23/2019 APPLICANT
Assigned to Plan Check Engineer 7/24/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 7/29/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/13/2019 MARJAN SHENASI
Building Plans Picked Up 8/15/2019 APPLICANT
Plan Check Approved 10/8/2019 VLADIMIR ARUTYUNYAN
Issued 10/11/2019 LADBS
CofO in Progress 10/31/2023 FARHAD DADBIN
Permit Finaled 11/1/2023 DAVID TSAU
CofO Issued 11/1/2023 DAVID TSAU
Permit Finaled 11/1/2023 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/23/2019 NIKTA MOUSAVI
Sewer availability Cleared 8/23/2019 NIKTA MOUSAVI
DAS Clearance Cleared 9/23/2019 VLADIMIR ARUTYUNYAN

Contact Information

Contractor The Moaddel Group Inc; Lic. No.: 1006915-B 905 S PRAIRIE AVE UNIT C      INGLEWOOD, CA 90301
Engineer Raeen,, Bahram; Lic. No.: C37060 11040 SANTA MONICA BLVD 326      LOS ANGELES, CA 90025

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2020 Not Ready for Inspection JASON BORUTA
Deputy Drilled-In Anchors 2/26/2020 Conditional Approval SORIN CIRSTOIU
Wood Frame 5/26/2021 Partial Inspection SORIN CIRSTOIU
Wood Frame 8/4/2021 Partial Approval SORIN CIRSTOIU
Drywall Nailing 8/24/2021 Partial Approval SORIN CIRSTOIU
Insulation 8/24/2021 Approved SORIN CIRSTOIU
Drywall Nailing 9/7/2021 Approved JOHN DODGE
T-Bar Ceiling 10/12/2021 Not Ready for Inspection JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Not Ready PAUL DAVIDSON
Final 9/23/2022 Corrections Issued PAUL DAVIDSON
METHANE-Final 9/23/2022 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 9/23/2022 Approved PAUL DAVIDSON
Final 10/26/2022 No Access for Inspection PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Not Ready PAUL DAVIDSON
Final 11/8/2022 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Not Ready SORIN CIRSTOIU
Final 10/31/2023 OK to Issue CofO FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV No Gas FARHAD DADBIN