2451 S PURDUE AVE 3-6 90064
Certificate Information: 2451 S PURDUE AVE 3-6 90064
- Application / Permit
- 19016-30000-17909
- Plan Check / Job No.
- B19WL03329
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PROPOSED ADDITION TO EXISTING UNIT #3&6, ADDITION WILL CREATE A 3RD STORY AS WELL AS A BEDROOM AND BATHROOM FOR EACH UNIT PER ZA-2019-6861-ZAA.
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2019 | APPLICANT |
| Green Plans Picked Up | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | MICHAEL LOPEZ |
| Corrections Issued | 7/16/2019 | MICHAEL LOPEZ |
| Quality Review Completed | 7/20/2019 | STANLEY RAAP |
| Building Plans Picked Up | 7/24/2019 | APPLICANT |
| Applicant returned to address corrections | 8/5/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/9/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/20/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/4/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 2/10/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/3/2022 | MICHAEL LOPEZ |
| Issued | 3/11/2022 | APPLICANT |
| CofO in Progress | 5/1/2023 | SORIN CIRSTOIU |
| Permit Finaled | 5/2/2023 | DAVID TSAU |
| CofO Issued | 5/2/2023 | DAVID TSAU |
| Permit Finaled | 5/2/2023 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 7/17/2019 | DONALD CRICHLOW |
| Housing rent stabilization | Cleared | 8/18/2021 | RICARDO BOHORQUEZ |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 9/27/2021 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dabby,, Yvette; Lic. No.: C22942 | 202 N MAPLE DR BEVERLY HILLS, CA 90210 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/22/2022 | Partial Inspection | JEFF BYTHEWAY |
| Pre-Inspection | 3/25/2022 | Approved | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 4/4/2022 | Partial Approval | ALAN NOVAK |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Approved | JEFF BYTHEWAY |
| Drywall Nailing | 5/19/2022 | Approved | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 5/19/2022 | Approved | JEFF BYTHEWAY |
| Final | 8/10/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 8/10/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Green Building Final | 8/10/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Green Building Rough | 8/10/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 8/10/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 8/10/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 8/26/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 9/8/2022 | Corrections Issued | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 9/8/2022 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 9/8/2022 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Rough | 9/8/2022 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 9/8/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 9/8/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 4/28/2023 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 4/28/2023 | Approved | SORIN CIRSTOIU |
| Green Building Final | 4/28/2023 | Approved | SORIN CIRSTOIU |
| Green Building Rough | 4/28/2023 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 4/28/2023 | Approved | SORIN CIRSTOIU |
| Wood Frame | 4/28/2023 | Conditional Approval | SORIN CIRSTOIU |
| Final | 5/1/2023 | OK to Issue CofO | SORIN CIRSTOIU |
| Wood Frame | 5/1/2023 | Approved | SORIN CIRSTOIU |