6223 N CLYBOURN AVE 91606

Certificate Information: 6223 N CLYBOURN AVE 91606

Application / Permit
19016-30000-16176
Plan Check / Job No.
B19WL03017
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) detached garage to ADU at rear of the lot.
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 KAVIAN REFAHI
Corrections Issued 5/30/2019 KAVIAN REFAHI
Plan Check Approved 7/10/2019 JAHANSHAH POURHASSAN
Issued 12/30/2020 APPLICANT
Building Plans Picked Up 1/7/2021 APPLICANT
CofO in Progress 1/27/2022 JACK KARGODORIAN
CofO Issued 1/29/2022 MICHAEL SMITH
Permit Finaled 1/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 6/12/2019 WALTER RAMIREZ
Address approval Cleared 6/24/2019 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 6/24/2019 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/24/2019 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/25/2021 Approved DANIEL DREW
Underground Mechanical 1/25/2021 Approved DANIEL DREW
Deputy Drilled-In Anchors 2/10/2021 Approved DANIEL DREW
Footing/Foundation/Slab 2/18/2021 Approved DANIEL DREW
PLUMBING-Rough 3/9/2021 Approved DANIEL DREW
ELECTRICAL-Rough 3/15/2021 Corrections Issued DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Approved DANIEL DREW
HVAC-Rough 3/15/2021 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 3/22/2021 Approved DANIEL DREW
ELECTRICAL-Rough 3/22/2021 Approved DANIEL DREW
HVAC-Rough 3/22/2021 Approved DANIEL DREW
Interior/Exterior Lathing 3/22/2021 Approved DANIEL DREW
Insulation 3/31/2021 Approved DANIEL DREW
Drywall Nailing 4/12/2021 Approved LILIANA PORTILLO
Pre-Inspection 4/12/2021 Approved JESUS RODRIGUEZ
Shower Pan 4/14/2021 Approved DANIEL DREW
Final 12/16/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/16/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 12/16/2021 Approved MISAEL ESPARZA
Final 1/20/2022 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Approved JACK KARGODORIAN