6223 N CLYBOURN AVE 91606
Certificate Information: 6223 N CLYBOURN AVE 91606
- Application / Permit
- 19016-30000-16176
- Plan Check / Job No.
- B19WL03017
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) detached garage to ADU at rear of the lot.
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | KAVIAN REFAHI |
| Corrections Issued | 5/30/2019 | KAVIAN REFAHI |
| Plan Check Approved | 7/10/2019 | JAHANSHAH POURHASSAN |
| Issued | 12/30/2020 | APPLICANT |
| Building Plans Picked Up | 1/7/2021 | APPLICANT |
| CofO in Progress | 1/27/2022 | JACK KARGODORIAN |
| CofO Issued | 1/29/2022 | MICHAEL SMITH |
| Permit Finaled | 1/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/12/2019 | WALTER RAMIREZ |
| Address approval | Cleared | 6/24/2019 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2019 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/24/2019 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/25/2021 | Approved | DANIEL DREW |
| Underground Mechanical | 1/25/2021 | Approved | DANIEL DREW |
| Deputy Drilled-In Anchors | 2/10/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 2/18/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 3/9/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 3/15/2021 | Corrections Issued | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 3/15/2021 | Not Ready for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 3/22/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 3/22/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 3/22/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 3/22/2021 | Approved | DANIEL DREW |
| Insulation | 3/31/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 4/12/2021 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 4/12/2021 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 4/14/2021 | Approved | DANIEL DREW |
| Final | 12/16/2021 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 12/16/2021 | Approved | MISAEL ESPARZA |
| Final | 1/20/2022 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | JACK KARGODORIAN |