979 N BEL-AIR ROAD 90077
Certificate Information: 979 N BEL-AIR ROAD 90077
- Application / Permit
- 19016-30000-15674
- Plan Check / Job No.
- B19WL02942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL KITCHEN AND BATH, ADD TO BATHROOM & ENCLOSE (E), LOGGIA AT SECOND STORM OVER (E) , ADD 1 STORY STORAGE UTILITY ROOM
- Permit Issued
- Issued on 8/15/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2019 | APPLICANT |
| Green Plans Picked Up | 6/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | MARJAN SHENASI |
| Corrections Issued | 6/17/2019 | MARJAN SHENASI |
| Quality Review Completed | 6/25/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/25/2019 | APPLICANT |
| Applicant returned to address corrections | 8/5/2019 | MARJAN SHENASI |
| Applicant returned to address corrections | 8/13/2019 | MARJAN SHENASI |
| Plan Check Approved | 8/15/2019 | MARJAN SHENASI |
| Issued | 8/15/2019 | LADBS |
| CofO in Progress | 9/1/2022 | CHRISTOPHER WILSON |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/3/2019 | STEVEN JIN |
| BHO/Hillside ordinance | Cleared | 7/3/2019 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2019 | STEVEN JIN |
| Sewer availability | Cleared | 7/3/2019 | STEVEN JIN |
| Green Code | Cleared | 7/18/2019 | DONALD CRICHLOW |
| GPI Written Notices | Cleared | 7/23/2019 | MARJAN SHENASI |
| Grading Pre-Inspection | Cleared | 7/23/2019 | MARJAN SHENASI |
| Miscellaneous | Cleared | 7/23/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/23/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/23/2019 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 8/5/2019 | CHRISTOPHER LAW |
| BHO/Hillside ordinance | Cleared | 8/13/2019 | NIKTA MOUSAVI |
Contact Information
| Architect | Parlee,, Eric Charles; Lic. No.: C9077 | 1750 OCEAN PARK BLVD SUITE 203 SANTA MONICA, CA 90405 |
| Contractor | Euro Builders Inc; Lic. No.: 634964-B | P O BOX 452634 LOS ANGELES, CA 90045 |
| Engineer | Howe,, Carl William; Lic. No.: C44773 | 4358 SEPULVEDA BLVD CULVER CITY, CA 90230 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/28/2019 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/29/2019 | Partial Approval | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 9/25/2019 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 9/26/2019 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/8/2019 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/25/2019 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 12/3/2019 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 1/15/2020 | Conditional Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 3/9/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 4/14/2020 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 5/1/2020 | Partial Approval | MATT KELLERMAN |
| Reinforced Concrete Frame | 6/3/2020 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 6/5/2020 | Partial Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 6/5/2020 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 6/17/2020 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 6/17/2020 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/2/2020 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 7/7/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/7/2020 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/30/2020 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/24/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Underground Mechanical | 9/11/2020 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 9/14/2020 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2020 | Partial Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 9/19/2020 | Partial Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 9/21/2020 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 9/23/2020 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 10/1/2020 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/1/2020 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/7/2020 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/16/2020 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 11/16/2020 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 12/7/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/7/2020 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 12/9/2020 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 12/17/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 12/17/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 12/18/2020 | Partial Approval | THOMAS FINNILA |
| Insulation | 12/22/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 1/7/2021 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 1/13/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Wood Frame | 1/13/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/22/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 1/22/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 1/22/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 1/28/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 1/28/2021 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/29/2021 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 1/29/2021 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 1/29/2021 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 1/29/2021 | Approved | CHRISTOPHER WILSON |
| Insulation | 2/11/2021 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 2/11/2021 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 3/3/2021 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 3/3/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Drywall Nailing | 3/8/2021 | Partial Approval | CHRISTOPHER WILSON |
| Service/Power Release | 5/6/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/12/2021 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 6/24/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 7/27/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 8/2/2021 | Partial Approval | CHRISTOPHER WILSON |
| Service/Power Release | 8/5/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 8/10/2021 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 10/1/2021 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/2/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 5/27/2022 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Final | 6/6/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/14/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Final | 6/14/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 6/14/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/16/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 6/16/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 6/16/2022 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 6/16/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/22/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 6/22/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 6/22/2022 | Approved | CHRISTOPHER WILSON |
| Final | 7/14/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 7/14/2022 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 8/31/2022 | Conditional Approval | CHRISTOPHER WILSON |