11257-11259 N DANUBE AVE 91344

Certificate Information: 11257-11259 N DANUBE AVE 91344

Application / Permit
19016-30000-13652
Plan Check / Job No.
B19WL02557
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) attached garage to accessory dwelling unit per AB494 & SB 229. All work per WFPP.
Permit Issued
Issued on 7/18/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 ALFREDO JARA
Corrections Issued 5/10/2019 ALFREDO JARA
Building Plans Picked Up 5/10/2019 APPLICANT
Plan Check Approved 7/9/2019 MANUEL GARCIA
Issued 7/18/2019 LADBS
CofO in Progress 6/20/2020 JENNIFER RABUCHIN
Permit Finaled 8/12/2020 MICHAEL SMITH
CofO Issued 8/12/2020 MICHAEL SMITH
Permit Finaled 8/12/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/13/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 6/13/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 6/13/2019 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 6/21/2019 BARTON HOLMES
Address approval Cleared 7/5/2019 STEVEN JIN
Permit Cleared 7/8/2019 JENNY CEA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/20/2019 Partial Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 10/22/2019 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 10/22/2019 Partial Approval JENNIFER RABUCHIN
Sewer 10/22/2019 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 10/25/2019 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 10/30/2019 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/1/2019 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/12/2019 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/12/2019 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/14/2019 Not Ready for Inspection PIERRE VEGA
BUILDING-Rough-Frame 11/19/2019 Approved MATTHEW NELSON
Drywall Nailing 11/19/2019 Not Ready for Inspection MATTHEW NELSON
Rough-Elec/Plmb/HVAC 11/19/2019 Approved MATTHEW NELSON
Insulation 11/21/2019 Approved JENNIFER RABUCHIN
Drywall Nailing 11/26/2019 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/26/2019 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/3/2019 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/24/2020 Corrections Issued JENNIFER RABUCHIN
Final 2/24/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/24/2020 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 2/24/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/24/2020 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/24/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/24/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/2/2020 Approved JENNIFER RABUCHIN
Final 3/2/2020 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/2/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/2/2020 Approved JENNIFER RABUCHIN
Service/Power Release 3/2/2020 Approved JENNIFER RABUCHIN