10248 W PENROSE ST 91352
Certificate Information: 10248 W PENROSE ST 91352
- Application / Permit
- 19016-30000-13447
- Plan Check / Job No.
- B19WL02533
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF 2ND FLOOR (CONVERT EXISTING ATTIC INTO 2ND FLOOR), AND CONVERT PORTION OF 1ST FLOOR GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, IN EXISTING 1-STORY TYPE VB DETACHED GARAGE.
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Valley
- Current Status
- Issued on 6/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 5/21/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 5/23/2019 | CORA JOHNSON |
| Building Plans Picked Up | 5/29/2019 | APPLICANT |
| Applicant returned to address corrections | 4/3/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 7/12/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 11/8/2023 | SERGIO SILVA |
| Applicant returned to address corrections | 11/27/2023 | SERGIO SILVA |
| Plan Check Approved | 12/11/2023 | SERGIO SILVA |
| No Progress | 2/23/2024 | SERGIO SILVA |
| Issued | 6/10/2024 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 10/28/2021 | RICHARD GARCIA |
| Address approval | Cleared | 5/16/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 5/16/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 5/16/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 5/16/2022 | JOSE DUARTE-DIAZ |
| ZA Case | Cleared | 5/17/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 5/17/2022 | RUBEN VASQUEZ |
| ZI | Cleared | 8/3/2022 | PEGGY MALONE-BROWN |
| Public Works-Highway Ded. | Cleared | 9/22/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 9/22/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 9/22/2022 | MEGAN GODINEZ |
| Private sewage disp. approval | Cleared | 1/30/2023 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 12/11/2023 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 12/11/2023 | KAMRAN GHOTBI RAVANDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2024 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 7/5/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 4/6/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/13/2026 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 4/21/2026 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/6/2026 | Approved | DAVID ANDERSON |
| FLOOD-Proofing Certificate | 5/27/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 5/27/2026 | Approved | DAVID ANDERSON |
| HVAC-Rough | 5/27/2026 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 5/27/2026 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 5/27/2026 | Corrections Issued | DAVID ANDERSON |