4848 E SAN MARCOS PL 90042
Certificate Information: 4848 E SAN MARCOS PL 90042
- Application / Permit
- 19016-30000-12144
- Plan Check / Job No.
- B19WL02296
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New two story ADU per Ordinance
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 5/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2019 | REZA HAGHIGHAT |
| Corrections Issued | 4/30/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 12/24/2020 | JASON JANGADA |
| Applicant returned to address corrections | 1/14/2021 | JASON JANGADA |
| Applicant returned to address corrections | 1/20/2022 | DANIEL SANJUAN |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 1/19/2023 | JAD BASMA |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 4/29/2026 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/4/2026 | DEROLD HAUFF |
| CofO Issued | 5/4/2026 | DEROLD HAUFF |
| Permit Finaled | 5/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2019 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 5/29/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 5/29/2019 | JEANETTE VONG |
| Miscellaneous | Cleared | 9/23/2020 | TERRY PHAN |
| Address approval | Cleared | 1/19/2023 | JEANETTE VONG |
| Address approval | Cleared | 1/19/2023 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2023 | JEANETTE VONG |
| GPI Written Notices | Cleared | 1/19/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 1/19/2023 | JAD BASMA |
| Hydrant and Access approval | Cleared | 1/19/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 1/19/2023 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 1/19/2023 | JEANETTE VONG |
| Sewer availability | Cleared | 1/19/2023 | JEANETTE VONG |
| Specific Plan | Cleared | 1/19/2023 | NASHYA JENSEN |
| ZI | Cleared | 1/19/2023 | NASHYA JENSEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 10/2/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 10/2/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/18/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Gas Test | 12/1/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/24/2026 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 3/24/2026 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 4/2/2026 | No Access for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/8/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/8/2026 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/24/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/28/2026 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/28/2026 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 4/28/2026 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 4/28/2026 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/28/2026 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/28/2026 | Approved | ALIZAH MAYAGOITIA |