5441 W 104TH ST 90045
Certificate Information: 5441 W 104TH ST 90045
- Application / Permit
- 19016-30000-07366
- Plan Check / Job No.
- B19WL01418
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (21) Motion Picture Studio
- Work Description
- T.I. and change of use from existing 185'-0" x 80'-8' warehouse to photo studio and interior alteration.
- Permit Issued
- Issued on 6/18/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | TROY DEGUZMAN |
| Corrections Issued | 4/1/2019 | TROY DEGUZMAN |
| Quality Review Completed | 4/10/2019 | MARJAN SHENASI |
| Building Plans Picked Up | 4/12/2019 | APPLICANT |
| Plan Check Approved | 6/13/2019 | TROY DEGUZMAN |
| Issued | 6/18/2019 | LADBS |
| CofO in Progress | 4/29/2020 | ALAN NOVAK |
| CofO in Progress | 4/29/2020 | ALAN NOVAK |
| Permit Finaled | 9/11/2020 | TED RIES |
| CofO Issued | 9/11/2020 | TED RIES |
| Permit Finaled | 9/11/2020 | TED RIES |
Permit Application Clearance Information
| DAS Clearance | Cleared | 5/30/2019 | TROY DEGUZMAN |
| Fire Marshall Fire Life Safety | Cleared | 6/5/2019 | DOMINIQUE MEDINA |
| Motion picture studio | Cleared | 6/5/2019 | DOMINIQUE MEDINA |
| Specific Plan | Cleared | 6/10/2019 | CLIVE GRAWE |
| ZI | Cleared | 6/11/2019 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2019 | CELINA MORENO |
| Sewer availability | Cleared | 6/13/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Architect | Ryder,, Eric Otto; Lic. No.: C32173 | 2004 19TH STREET SANTA MONICA, CA 90404 |
| Contractor | Kaesler Plumbing Inc; Lic. No.: 842715-B | 1135 GREEN LANE LA CANADA, CA 91011 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 7/17/2019 | Corrections Issued | ALAN NOVAK |
| Insulation | 8/27/2019 | Approved | ALAN NOVAK |
| Wood Frame | 8/27/2019 | Approved | ALAN NOVAK |
| Final | 12/23/2019 | Not Ready for Inspection | ALAN NOVAK |
| Reinforced Concrete Frame | 12/23/2019 | Not Ready for Inspection | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 12/23/2019 | SGSOV Not Ready | ALAN NOVAK |
| Smoke Detectors | 12/23/2019 | Not Ready for Inspection | ALAN NOVAK |
| Final | 4/10/2020 | Corrections Issued | ALAN NOVAK |
| Reinforced Concrete Frame | 4/10/2020 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 4/10/2020 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 4/10/2020 | Approved | ALAN NOVAK |
| Final | 4/17/2020 | OK to Issue CofO | ALAN NOVAK |