8740 S SEPULVEDA BLVD #105 90045
Certificate Information: 8740 S SEPULVEDA BLVD #105 90045
- Application / Permit
- 19016-30000-02806
- Plan Check / Job No.
- B19WL00479
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Tenant improvement and change of use to new retail space.
- Permit Issued
- Issued on 5/3/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2019 | MARJAN SHENASI |
| Corrections Issued | 2/19/2019 | MARJAN SHENASI |
| Disabled Access Plans Picked Up | 2/22/2019 | APPLICANT |
| Quality Review Completed | 2/27/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/28/2019 | APPLICANT |
| Applicant returned to address corrections | 3/15/2019 | MARJAN SHENASI |
| Plan Check Approved | 4/25/2019 | MARJAN SHENASI |
| Issued | 5/3/2019 | LADBS |
| CofO in Progress | 1/31/2022 | GRANT WOODS |
| Permit Finaled | 2/14/2022 | DAVID TSAU |
| CofO Issued | 2/14/2022 | DAVID TSAU |
| Permit Finaled | 2/14/2022 | DAVID TSAU |
Permit Application Clearance Information
| ZA Case | Cleared | 3/4/2019 | DAVID TEHRANI |
| "D" conditions | Cleared | 3/6/2019 | DAVID TEHRANI |
| "Q" conditions | Cleared | 3/6/2019 | DAVID TEHRANI |
| Miscellaneous | Cleared | 3/6/2019 | DAVID TEHRANI |
| Miscellaneous | Cleared | 3/6/2019 | DAVID TEHRANI |
| ZA Case | Cleared | 3/6/2019 | DAVID TEHRANI |
| ZA Case | Cleared | 3/6/2019 | DAVID TEHRANI |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2019 | DENNIS BRAGIN |
| Sewer availability | Cleared | 3/7/2019 | DENNIS BRAGIN |
| DAS Clearance | Cleared | 3/14/2019 | SOMKIAT SUPANYACHOTSKUL |
| ZI | Cleared | 3/26/2019 | DAVID TEHRANI |
| Specific Plan | Cleared | 3/27/2019 | EDER ROMERO |
Contact Information
| Architect | Nouizi,, Ilyes M; Lic. No.: C32135 | 14252 CULVER DRIVE SUITE A-605 IRVINE, CA 92604 |
| Contractor | J T M Construction Group Inc; Lic. No.: 956584-B | 44 WEST 28TH STREET 11TH FLOOR NEW YORK, NY 10001 |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 4215 TOLAND WAY LOS ANGELES, CA 90065 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/23/2019 | Partial Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 7/23/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/26/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/5/2019 | Approved | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 8/5/2019 | Partial Approval | NICK LAROCCA |
| Footing/Foundation/Slab | 8/5/2019 | Partial Approval | NICK LAROCCA |
| Deputy Drilled-In Anchors | 8/6/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 8/7/2019 | Conditional Approval | ALAN NOVAK |
| Wall Anchors | 8/7/2019 | Partial Inspection | ALAN NOVAK |
| Wood Frame | 8/7/2019 | Partial Inspection | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/8/2019 | Conditional Approval | ALAN NOVAK |
| Pre-Inspection | 8/14/2019 | Approved | ALAN NOVAK |
| Deputy Steel/Welding | 8/15/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/21/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 8/23/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/6/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 9/9/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/9/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/10/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/11/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 9/12/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/12/2019 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 9/12/2019 | Partial Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 9/13/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/13/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/16/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/17/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/18/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/19/2019 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 9/20/2019 | Partial Approval | ALAN NOVAK |
| Wood Frame | 9/20/2019 | Partial Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/24/2019 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 9/27/2019 | Partial Approval | ALAN NOVAK |
| Pre-Inspection | 10/2/2019 | Approved | ALAN NOVAK |
| Drywall Nailing | 10/18/2019 | Partial Approval | ALAN NOVAK |
| Final | 1/31/2022 | Conditional Approval | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 1/31/2022 | Approved | GRANT WOODS |
| Wood Frame | 1/31/2022 | Approved | GRANT WOODS |