1138 S ALFRED ST 90035

Certificate Information: 1138 S ALFRED ST 90035

Application / Permit
19016-30000-00913
Plan Check / Job No.
B19WL00138
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE 18' 2" X 18' 2" TO ADU PER AB 494 AND SB 299. construction per WFPP.
Permit Issued
Issued on 1/17/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2019 APPLICANT
Assigned to Plan Check Engineer 1/17/2019 RICARDO RAMIREZ
Corrections Issued 1/22/2019 RICARDO RAMIREZ
Building Plans Picked Up 1/29/2019 APPLICANT
Plan Check Approved 1/17/2020 KAVIAN REFAHI
Issued 1/17/2020 LADBS
CofO in Progress 8/10/2020 DAVID CHAN
Permit Finaled 2/13/2021 DEROLD HAUFF
CofO Issued 2/13/2021 DEROLD HAUFF
Permit Finaled 2/13/2021 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 3/14/2019 MAX LODER
ZI Cleared 3/14/2019 MAX LODER
Construction within easement Cleared 8/17/2019 RIDWAN HARDY
Address approval Cleared 12/30/2019 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/30/2019 DINAH GARIN
Sewer availability Cleared 12/30/2019 DINAH GARIN

Contact Information

Contractor Soumekh Michael N; Lic. No.: 773770-B 1140 SOUTH ALFRED STREET      LOS ANGELES, CA 90035

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/9/2020 Conditional Approval MATTHEW NUCKOLLS
Footing/Foundation/Slab 3/9/2020 Approved DAVID CHAN
PLUMBING-Rough 4/8/2020 Corrections Issued DAVID CHAN
Underground Mechanical 4/16/2020 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 4/24/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 5/6/2020 Approved DAVID CHAN
METHANE-Rough 5/6/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 5/8/2020 Not Ready for Inspection SABAS ALONSO
Insulation 5/8/2020 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 5/8/2020 Not Ready for Inspection SABAS ALONSO
Insulation 5/12/2020 Approved THOMAS LOGRASSO
Drywall Nailing 5/14/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/20/2020 Approved SABAS ALONSO
Shower Pan 5/20/2020 Approved SABAS ALONSO
Footing/Foundation/Slab 5/22/2020 Partial Approval DAVID CHAN
Final 7/6/2020 Corrections Issued DAVID CHAN
SGSOV-Seismic Gas S/O Valve 7/6/2020 SGSOV Not Ready DAVID CHAN
Smoke Detectors 7/6/2020 Approved DAVID CHAN
Final 8/7/2020 OK to Issue CofO DAVID CHAN
SGSOV-Seismic Gas S/O Valve 8/7/2020 SGSOV Approved DAVID CHAN