658-660 W SEPULVEDA ST 90731
Certificate Information: 658-660 W SEPULVEDA ST 90731
- Application / Permit
- 19016-20004-32944
- Plan Check / Job No.
- B20VN11517
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- SUPPLEMENTAL PERMIT TO REVISE SCOPE OF WORK TO CONVERT (E) SINGLE FAMILY DWELLING TO DUPLEX AND CONVERT ATTIC SPACE TO THIRD FLOOR BEDROOM AND BATHROOM.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/6/2020 | JEROME MAGAT PALMA |
| Issued | 10/9/2020 | APPLICANT |
| Permit Finaled | 5/24/2021 | ANDREW BEELI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 11/4/2020 | Corrections Issued | ANDREW BEELI |
| Wood Frame | 11/20/2020 | Corrections Issued | ANDREW BEELI |
| Deputy Wood Construction | 11/24/2020 | Partial Approval | ANDREW BEELI |
| Wood Frame | 11/24/2020 | Not Ready for Inspection | ANDREW BEELI |
| Wood Frame | 12/1/2020 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 12/23/2020 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 12/28/2020 | Corrections Issued | ANDREW BEELI |
| Insulation | 12/30/2020 | Approved | ANDREW BEELI |
| Drywall Nailing | 1/15/2021 | Corrections Issued | ANDREW BEELI |
| Interior/Exterior Lathing | 1/15/2021 | Approved | ANDREW BEELI |
| Final | 1/19/2021 | Not Ready for Inspection | ANDREW BEELI |
| Wood Frame | 1/19/2021 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 1/25/2021 | Corrections Issued | ANDREW BEELI |
| Interior/Exterior Lathing | 1/27/2021 | Approved | ANDREW BEELI |
| Final | 2/12/2021 | Corrections Issued | ANDREW BEELI |
| Final | 3/23/2021 | Not Ready for Inspection | ANDREW BEELI |
| Final | 4/6/2021 | Not Ready for Inspection | ANDREW BEELI |
| Pre-Inspection | 4/26/2021 | Corrections Issued | ANDREW BEELI |
| Final | 5/3/2021 | Not Ready for Inspection | ANDREW BEELI |
| Final | 5/18/2021 | Corrections Issued | ANDREW BEELI |