658-660 W SEPULVEDA ST 90731

Certificate Information: 658-660 W SEPULVEDA ST 90731

Application / Permit
19016-20004-32944
Plan Check / Job No.
B20VN11517
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
SUPPLEMENTAL PERMIT TO REVISE SCOPE OF WORK TO CONVERT (E) SINGLE FAMILY DWELLING TO DUPLEX AND CONVERT ATTIC SPACE TO THIRD FLOOR BEDROOM AND BATHROOM.
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
Permit Finaled on 5/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/6/2020 JEROME MAGAT PALMA
Plan Check Approved 10/6/2020 JEROME MAGAT PALMA
Issued 10/9/2020 APPLICANT
Permit Finaled 5/24/2021 ANDREW BEELI

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 11/4/2020 Corrections Issued ANDREW BEELI
Wood Frame 11/20/2020 Corrections Issued ANDREW BEELI
Deputy Wood Construction 11/24/2020 Partial Approval ANDREW BEELI
Wood Frame 11/24/2020 Not Ready for Inspection ANDREW BEELI
Wood Frame 12/1/2020 Not Ready for Inspection ANDREW BEELI
Insulation 12/23/2020 Not Ready for Inspection ANDREW BEELI
Insulation 12/28/2020 Corrections Issued ANDREW BEELI
Insulation 12/30/2020 Approved ANDREW BEELI
Drywall Nailing 1/15/2021 Corrections Issued ANDREW BEELI
Interior/Exterior Lathing 1/15/2021 Approved ANDREW BEELI
Final 1/19/2021 Not Ready for Inspection ANDREW BEELI
Wood Frame 1/19/2021 Approved ANDREW BEELI
Interior/Exterior Lathing 1/25/2021 Corrections Issued ANDREW BEELI
Interior/Exterior Lathing 1/27/2021 Approved ANDREW BEELI
Final 2/12/2021 Corrections Issued ANDREW BEELI
Final 3/23/2021 Not Ready for Inspection ANDREW BEELI
Final 4/6/2021 Not Ready for Inspection ANDREW BEELI
Pre-Inspection 4/26/2021 Corrections Issued ANDREW BEELI
Final 5/3/2021 Not Ready for Inspection ANDREW BEELI
Final 5/18/2021 Corrections Issued ANDREW BEELI