15420-15420 1/2 W STAGG ST 91406

Certificate Information: 15420-15420 1/2 W STAGG ST 91406

Application / Permit
19016-20003-34151
Plan Check / Job No.
B20VN05660
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO PERMIT #19016-20000-34151 TO REVISE SCOPE OF WORK TO READ "CONVERT ATTACHED 18' X 18' CARPORT TO JUNIOR ADU." ALL WORK DONE PER WFPP.
Permit Issued
Issued on 5/28/2020
Issuing Office
Valley
Current Status
Permit Finaled on 3/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2020 APPLICANT
Assigned to Plan Check Engineer 4/27/2020 GURUNATH NESARAJAH
Corrections Issued 4/29/2020 GURUNATH NESARAJAH
Plan Check Approved 5/20/2020 GURUNATH NESARAJAH
Issued 5/28/2020 LADBS
Permit Finaled 3/23/2021 CHRISTOPHE COCHRAN

Permit Application Clearance Information

Address approval Cleared 4/29/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/29/2020 ADRIAN CASTRO
Sewer availability Cleared 4/29/2020 ADRIAN CASTRO

Contact Information

Contractor Markas Design & Construction; Lic. No.: 832632-B 6022 VANTAGE AVENUE      NORTH HOLLYWOOD, CA 91606

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/29/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 5/29/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/29/2020 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 6/9/2020 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 6/9/2020 Approved WILLIAM KUEHN
Insulation 6/10/2020 Approved ARAM AVEDISIAN
Drywall Nailing 6/16/2020 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 9/4/2020 Not Ready for Inspection GREGG CUMMINGS
Final 9/4/2020 Not Ready for Inspection GREGG CUMMINGS
Green Building Final 9/4/2020 Corrections Issued GREGG CUMMINGS
Green Building Rough 9/4/2020 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 9/4/2020 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 9/17/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/17/2020 Approved JENNIFER RABUCHIN
Final 9/17/2020 Partial Inspection JENNIFER RABUCHIN
Green Building Final 9/17/2020 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 9/17/2020 Approved JENNIFER RABUCHIN
HVAC-Final 9/17/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/17/2020 Approved JENNIFER RABUCHIN
Smoke Detectors 9/17/2020 Approved JENNIFER RABUCHIN
Final 3/23/2021 Permit Finaled CHRISTOPHE COCHRAN
Green Building Final 3/23/2021 Approved CHRISTOPHE COCHRAN