18517 W VENTURA BLVD 91356
Certificate Information: 18517 W VENTURA BLVD 91356
- Application / Permit
- 19016-20002-15124
- Plan Check / Job No.
- B21VN11680
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- SUPPLEMENTAL PERMIT TO 19016-20002-15124 TO REVISE FLOOR PLAN AND RECHECK LOST PLANS
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- Issued on 11/3/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | SELLA BENYAMIN |
| Corrections Issued | 8/27/2021 | SELLA BENYAMIN |
| Plan Check Approved | 10/13/2021 | SELLA BENYAMIN |
| Issued | 11/3/2021 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 9/7/2021 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Palomo'S Construction; Lic. No.: 633870-B | 6110 ROD AVE WOODLAND HILLS, CA 91367 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2022 | Partial Approval | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 3/7/2022 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 3/14/2022 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 3/17/2022 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 4/29/2022 | Partial Inspection | JEFFREY FULTON |
| Pre-Inspection | 2/2/2024 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 7/23/2024 | Corrections Issued | BRIAN KELLY |
| Wood Frame | 7/1/2025 | Corrections Issued | BRIAN KELLY |
| Wood Frame | 8/15/2025 | Partial Inspection | BRIAN KELLY |
| Wood Frame | 8/22/2025 | No Access for Inspection | BRIAN KELLY |
| Insulation | 10/20/2025 | No Access for Inspection | ROBERT DAVIS |
| Insulation | 10/23/2025 | Partial Inspection | BRIAN KELLY |
| Drywall Nailing | 1/23/2026 | No Access for Inspection | BRIAN KELLY |
| Drywall Nailing | 1/27/2026 | Approved | BRIAN KELLY |