7847 N AGNES AVE 91605
Certificate Information: 7847 N AGNES AVE 91605
- Application / Permit
- 19016-20001-27679
- Plan Check / Job No.
- B21VN00079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO PERMIT #: 19016-20000-27679 TO ADD 21'-0" X 22'-10" TO AN EXISTING DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/19/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2021 | JENNIFER LEE |
| Corrections Issued | 3/1/2021 | JENNIFER LEE |
| Plan Check Approved | 5/18/2021 | JENNIFER LEE |
| Issued | 5/19/2021 | APPLICANT |
| Building Plans Picked Up | 5/19/2021 | APPLICANT |
| Permit Finaled | 4/27/2022 | CHRISTOPHER DELLEFIELD |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/17/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/18/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/5/2021 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/10/2021 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 8/17/2021 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 8/19/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 8/23/2021 | Approved | JOHN HAYES |
| PLUMBING-Rough | 8/23/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 9/23/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 9/23/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/12/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/12/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/12/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/12/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/18/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/18/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 11/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/15/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 11/15/2021 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 11/15/2021 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/8/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 12/8/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 12/17/2021 | Approved | GREGG CUMMINGS |
| Shower Pan | 12/17/2021 | Approved | GREGG CUMMINGS |
| Final | 4/27/2022 | Permit Finaled | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/27/2022 | Approved | CHRISTOPHER DELLEFIELD |