12417 W VENTURA CT 91604
Certificate Information: 12417 W VENTURA CT 91604
- Application / Permit
- 19016-20001-20098
- Plan Check / Job No.
- B19VN17426
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (21) Showcase Theatre
- Work Description
- SUPPLEMENTAL PERMIT FOR 19016-20000-20098 TO REVISE ARCHITECTURAL & STRUCTURAL PLANS: SPIRAL STAIRS TO (E) MEZZANINE, RELOCATE HANDICAP BATHROOMS, RELOCATE NON-BEARING WALLS AND ADD NON-ACCESSIBLE BATHROOM
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/30/2021
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/10/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/6/2019 | NILOOFAR MEHRAIN |
| Issued | 1/8/2020 | LADBS |
| Permit Finaled | 6/30/2021 | ROBERT DAVIS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2019 | EMIL KYUPELYAN |
| Hold | Cleared | 10/10/2019 | NILOOFAR MEHRAIN |
| Sewer availability | Cleared | 10/10/2019 | EMIL KYUPELYAN |
| Fire Marshall Fire Life Safety | Cleared | 11/8/2019 | OSCAR SALGADO JR |
| Miscellaneous | Cleared | 12/4/2019 | HERMINIGILDO AGUSTIN |
| Specific Plan | Cleared | 12/4/2019 | HERMINIGILDO AGUSTIN |
| ZI | Cleared | 12/4/2019 | HERMINIGILDO AGUSTIN |
| ZI | Cleared | 12/4/2019 | HERMINIGILDO AGUSTIN |
| DAS Clearance | Cleared | 1/7/2020 | NILOOFAR MEHRAIN |
| Hold | Cleared | 3/2/2020 | JEREMY CORONEL |
Contact Information
| Architect | Sullivan,, Scott Bernard; Lic. No.: C33139 | 828 11TH STREET # 5 SANTA MONICA, CA 90403 |
| Contractor | Hogan Buffa Building; Lic. No.: 939214-B | 469 W AVENUE 37 LOS ANGELES, CA 90065 |
| Engineer | Cosentino,, Joseph; Lic. No.: C53176 | 820 ISABELLA MONTEREY PARK, CA 91754 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 8/12/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 8/18/2020 | Approved | ROBERT DAVIS |
| Pre-Inspection | 11/19/2020 | Approved | ROBERT DAVIS |
| Final | 6/17/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 6/30/2021 | Permit Finaled | ROBERT DAVIS |