2006 N SERRANO AVE 90027

Certificate Information: 2006 N SERRANO AVE 90027

Application / Permit
19016-20001-11637
Plan Check / Job No.
B20VN10059
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLMENTAL PERMIT TO 19016-20000-11637 TO REVISE FRAMING AND FOUNDATION PLANS.
Permit Issued
Issued on 12/22/2020
Issuing Office
Current Status
Permit Finaled on 9/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2020 APPLICANT
Assigned to Plan Check Engineer 8/12/2020 RAPHAEL ROSAS
Corrections Issued 8/15/2020 RAPHAEL ROSAS
Issued 12/22/2020 APPLICANT
Permit Finaled 8/19/2021 JOHN TCHANG
Permit Finaled 9/1/2021 JOHN TCHANG

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/19/2020 ALEXANDER ANDREWS

Contact Information

Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411
Engineer Standley,, Craig Erick; Lic. No.: C87675 6631 MURIETTA AVE      LOS ANGELES, CA 91405

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN FRANCHINI, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/16/2021 Approved JOHN TCHANG
Footing/Foundation/Slab 3/16/2021 Approved JOHN TCHANG
Piling/Pier/Caisson 3/16/2021 Not Ready for Inspection JOHN TCHANG
Reinforced Concrete Frame 3/16/2021 Not Ready for Inspection JOHN TCHANG
Excavation/Setback/Form/Re-Bar 3/30/2021 Corrections Issued JOHN TCHANG
Footing/Foundation/Slab 3/30/2021 Not Ready for Inspection JOHN TCHANG
Light Gage Steel Frame 3/30/2021 Not Ready for Inspection JOHN TCHANG
Piling/Pier/Caisson 3/30/2021 Not Ready for Inspection JOHN TCHANG
Reinforced Concrete Frame 3/30/2021 Not Ready for Inspection JOHN TCHANG
Reinforced Masonry Frame 3/30/2021 Not Ready for Inspection JOHN TCHANG
Structural Steel Frame 3/30/2021 Not Ready for Inspection JOHN TCHANG
Wood Frame 3/30/2021 Not Ready for Inspection JOHN TCHANG
Excavation/Setback/Form/Re-Bar 3/31/2021 Approved JOHN TCHANG
Footing/Foundation/Slab 3/31/2021 Approved JOHN TCHANG
Light Gage Steel Frame 3/31/2021 Approved JOHN TCHANG
Masonry Wall/Backfill 3/31/2021 Not Ready for Inspection JOHN TCHANG
Piling/Pier/Caisson 3/31/2021 Approved JOHN TCHANG
Reinforced Concrete Frame 3/31/2021 Approved JOHN TCHANG
Reinforced Masonry Frame 3/31/2021 Approved JOHN TCHANG
Structural Steel Frame 3/31/2021 Approved JOHN TCHANG
Wood Frame 3/31/2021 Not Ready for Inspection JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Not Ready for Inspection JOHN TCHANG
Footing/Foundation/Slab 4/14/2021 Not Ready for Inspection JOHN TCHANG
Insulation 4/14/2021 Not Ready for Inspection JOHN TCHANG
Light Gage Steel Frame 4/14/2021 Not Ready for Inspection JOHN TCHANG
Masonry Wall/Backfill 4/14/2021 Not Ready for Inspection JOHN TCHANG
Reinforced Concrete Frame 4/14/2021 Not Ready for Inspection JOHN TCHANG
Reinforced Masonry Frame 4/14/2021 Not Ready for Inspection JOHN TCHANG
Structural Steel Frame 4/14/2021 Not Ready for Inspection JOHN TCHANG
Wall Anchors 4/14/2021 Not Ready for Inspection JOHN TCHANG
Wood Frame 4/14/2021 Not Ready for Inspection JOHN TCHANG
Excavation/Setback/Form/Re-Bar 4/19/2021 Not Ready for Inspection JOHN TCHANG
Footing/Foundation/Slab 4/19/2021 Not Ready for Inspection JOHN TCHANG
Light Gage Steel Frame 4/19/2021 Not Ready for Inspection JOHN TCHANG
Piling/Pier/Caisson 4/19/2021 Not Ready for Inspection JOHN TCHANG
Reinforced Concrete Frame 4/19/2021 Not Ready for Inspection JOHN TCHANG
Reinforced Masonry Frame 4/19/2021 Not Ready for Inspection JOHN TCHANG
Structural Steel Frame 4/19/2021 Not Ready for Inspection JOHN TCHANG
Wood Frame 4/19/2021 Not Ready for Inspection JOHN TCHANG
Structural Steel Frame 4/20/2021 Not Ready for Inspection JOHN TCHANG
Wood Frame 4/20/2021 Not Ready for Inspection JOHN TCHANG
Footing/Foundation/Slab 4/21/2021 Approved JOHN TCHANG
Light Gage Steel Frame 4/21/2021 Corrections Issued JOHN TCHANG
Structural Steel Frame 4/21/2021 Approved JOHN TCHANG
Wood Frame 4/21/2021 Not Ready for Inspection JOHN TCHANG
Drywall Nailing 5/3/2021 Not Ready for Inspection JOHN TCHANG
Insulation 5/3/2021 Conditional Approval JOHN TCHANG
Interior/Exterior Lathing 5/3/2021 Corrections Issued JOHN TCHANG
Special/Order Compliance 5/3/2021 Corrections Issued JOHN TCHANG
Final 5/10/2021 Corrections Issued JOHN TCHANG
Drywall Nailing 5/18/2021 Not Ready for Inspection JOHN TCHANG
Drywall Nailing 6/15/2021 Approved JOHN TCHANG
Final 6/15/2021 Corrections Issued JOHN TCHANG
Final 8/2/2021 Corrections Issued JOHN TCHANG
Final 8/11/2021 Not Ready for Inspection JOHN TCHANG
Final 8/19/2021 Permit Finaled JOHN TCHANG