6618 N ATOLL AVE 91606

Certificate Information: 6618 N ATOLL AVE 91606

Application / Permit
19016-20000-41423
Plan Check / Job No.
B19VN22780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-2" X 20'-1" DETACHED GARAGE AND ADD 2'-9" X 16'-2" FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/31/2020
Issuing Office
Current Status
CofO Issued on 3/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 JENNIFER LEE
Corrections Issued 1/7/2020 JENNIFER LEE
Applicant returned to address corrections 6/18/2020 JEFFREY TANGONAN
Plan Check Approved 10/29/2020 JENNIFER LEE
Issued 12/31/2020 APPLICANT
CofO in Progress 1/9/2026 WAYNE REGESTER
Permit Finaled 3/12/2026 RUBEN SALAS
CofO Issued 3/12/2026 RUBEN SALAS
Permit Finaled 3/12/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/9/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/9/2020 ADRIAN CASTRO
Sewer availability Cleared 6/9/2020 ADRIAN CASTRO
Construction near power lines Cleared 10/13/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Mahjoub,, Nina Azadeh; Lic. No.: C78947 21400 BURBANK BLVD 114      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2021 Approved BRENDAN LOONEY
Sewer 5/7/2021 Partial Inspection RICHARD DOCKUS
PLUMBING-Rough 6/16/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 6/29/2021 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 6/29/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 6/29/2021 Conditional Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 7/8/2021 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 7/8/2021 Not Ready for Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 8/3/2021 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 8/3/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 3/21/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 8/23/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/27/2023 Approved KIRK SANDERS
Underground Mechanical 9/27/2023 Partial Approval KIRK SANDERS
Drywall Nailing 2/14/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 2/14/2024 Corrections Issued JOSE AVILA
HVAC-Rough 2/14/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 2/14/2024 Corrections Issued JOSE AVILA
Drywall Nailing 4/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 4/8/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 4/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 4/8/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 8/5/2024 Not Ready for Inspection LOUIS ESCOTO
Green Building Rough 8/5/2024 Approved LOUIS ESCOTO
HVAC-Rough 8/5/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 8/8/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 8/8/2024 Partial Approval OGANES TARAKHCHYAN
Insulation 8/29/2024 No Access for Inspection OGANES TARAKHCHYAN
Insulation 9/9/2024 Conditional Approval LOUIS ESCOTO
Drywall Nailing 10/3/2024 Approved OGANES TARAKHCHYAN
Shower Pan 11/27/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Final 9/5/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Ready OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/15/2025 Approved WAYNE REGESTER
ELECTRICAL-Final 10/15/2025 Not Ready for Inspection WAYNE REGESTER
Final 10/15/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 10/15/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Final 10/15/2025 Approved WAYNE REGESTER
PLUMBING-Final 10/15/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Not Required WAYNE REGESTER
Smoke Detectors 10/15/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 10/21/2025 Corrections Issued OGANES TARAKHCHYAN
Final 10/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 10/21/2025 Approved OGANES TARAKHCHYAN
Smoke Detectors 10/21/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 10/31/2025 Approved WAYNE REGESTER
Final 10/31/2025 Corrections Issued WAYNE REGESTER
HVAC-Final 10/31/2025 Not Ready for Inspection WAYNE REGESTER
Final 11/18/2025 Partial Inspection WAYNE REGESTER
Final 1/9/2026 OK to Issue CofO WAYNE REGESTER