6618 N ATOLL AVE 91606
Certificate Information: 6618 N ATOLL AVE 91606
- Application / Permit
- 19016-20000-41423
- Plan Check / Job No.
- B19VN22780
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-2" X 20'-1" DETACHED GARAGE AND ADD 2'-9" X 16'-2" FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/31/2020
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2020 | JENNIFER LEE |
| Corrections Issued | 1/7/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 6/18/2020 | JEFFREY TANGONAN |
| Plan Check Approved | 10/29/2020 | JENNIFER LEE |
| Issued | 12/31/2020 | APPLICANT |
| CofO in Progress | 1/9/2026 | WAYNE REGESTER |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
| CofO Issued | 3/12/2026 | RUBEN SALAS |
| Permit Finaled | 3/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 10/13/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahjoub,, Nina Azadeh; Lic. No.: C78947 | 21400 BURBANK BLVD 114 WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/24/2021 | Approved | BRENDAN LOONEY |
| Sewer | 5/7/2021 | Partial Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 6/16/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/29/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/29/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 6/29/2021 | Conditional Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 7/8/2021 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/8/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 8/3/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/3/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/21/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 8/23/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/27/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 9/27/2023 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 2/14/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 2/14/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 2/14/2024 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 2/14/2024 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 4/8/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 4/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/5/2024 | Not Ready for Inspection | LOUIS ESCOTO |
| Green Building Rough | 8/5/2024 | Approved | LOUIS ESCOTO |
| HVAC-Rough | 8/5/2024 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 8/8/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 8/8/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/29/2024 | No Access for Inspection | OGANES TARAKHCHYAN |
| Insulation | 9/9/2024 | Conditional Approval | LOUIS ESCOTO |
| Drywall Nailing | 10/3/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 11/27/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 9/5/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/15/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 10/15/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 10/15/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 10/15/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 10/15/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 10/15/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Not Required | WAYNE REGESTER |
| Smoke Detectors | 10/15/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Final | 10/21/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 10/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 10/21/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/21/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/31/2025 | Approved | WAYNE REGESTER |
| Final | 10/31/2025 | Corrections Issued | WAYNE REGESTER |
| HVAC-Final | 10/31/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 11/18/2025 | Partial Inspection | WAYNE REGESTER |
| Final | 1/9/2026 | OK to Issue CofO | WAYNE REGESTER |