1287 N CASIANO ROAD 90049
Certificate Information: 1287 N CASIANO ROAD 90049
- Application / Permit
- 19016-20000-41388
- Plan Check / Job No.
- B19VN22736
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD - KITCHEN & BATHROOMS REMODEL, CONVERT (E) STORAGE TO LAUNDRY ROOM, CONVERT (E) FAMILY & LAUNDRY ROOM TO (N) BEDROOM / CLOSET & BATHROOM PER ENGINEERING.
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 5/18/2021
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 12/31/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 1/7/2020 | JENNIFER LEE |
| Issued | 12/17/2020 | APPLICANT |
| Permit Finaled | 5/18/2021 | CARLOS MATAMOROS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2019 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 12/31/2019 | MANUEL TEJADA |
| Sewer availability | Cleared | 12/31/2019 | LEE GUILBEAUX |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | M Y Construction Inc; Lic. No.: 1036168-B | 10116 HILLGROVE DRIVE BEVERLY HILLS, CA 90210 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/22/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 1/19/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/19/2021 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 1/19/2021 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/21/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/21/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Conditional Approval | CARLOS MATAMOROS |
| MERV13>=Rough | 1/21/2021 | Approved | CARLOS MATAMOROS |
| Wood Frame | 1/21/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 1/26/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/26/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 1/26/2021 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 1/28/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/28/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/11/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/13/2021 | Corrections Issued | CARLOS MATAMOROS |
| Final | 5/13/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 5/13/2021 | Corrections Issued | CARLOS MATAMOROS |
| MERV13>=Final | 5/13/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 5/13/2021 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 5/13/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/18/2021 | Approved | CARLOS MATAMOROS |
| Final | 5/18/2021 | Permit Finaled | CARLOS MATAMOROS |
| HVAC-Final | 5/18/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 5/18/2021 | Approved | CARLOS MATAMOROS |