1358 N MILLER DR 90069
Certificate Information: 1358 N MILLER DR 90069
- Application / Permit
- 19016-20000-41350
- Plan Check / Job No.
- B19VN22719
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- PROPOSED STRUCTURAL ATERATION AND ADD NEW ROOF TO THE (E) DETACHED GARAGE. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Current Status
- Permit Finaled on 1/19/2024
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 2/18/2020 | SARKIS HARABEDIAN |
| Quality Review Completed | 2/25/2020 | GUANG MIN TUNG |
| Green Plans Picked Up | 6/1/2020 | APPLICANT |
| Applicant returned to address corrections | 6/16/2020 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 6/22/2021 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| Applicant returned to address corrections | 7/27/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/28/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 11/18/2022 | SARKIS HARABEDIAN |
| Issued | 1/5/2023 | APPLICANT |
| Permit Finaled | 1/19/2024 | RAUL BARAJAS |
Permit Application Clearance Information
| Hold | Cleared | 2/18/2020 | LOURDES RAMIRO |
| Grading Pre-Inspection | Cleared | 9/18/2020 | SARKIS HARABEDIAN |
| Roof/Waste drainage to street | Cleared | 2/22/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | WALLIE JONG |
Contact Information
| Architect | Kirollos,, Elhamy Michel; Lic. No.: C30861 | 409 ORANGE AVENUE #4 LONG BEACH, CA 90802 |
| Contractor | M A H And Son Builders Inc; Lic. No.: 1002124-B | 11301 W OLYMPIC BLVD #537 LOS ANGELES, CA 90064 |
| Engineer | Bejarano,, David Alberto; Lic. No.: C81225 | 9740 ZELZAH AVE 237 NORTHRIDGE, CA 91325 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/15/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Grading Pre-Inspection | 5/15/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Structural Steel Frame | 5/15/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/12/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/16/2023 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Approved | RAUL BARAJAS |
| Wood Frame | 9/7/2023 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 9/22/2023 | Approved | RAUL BARAJAS |
| Final | 12/29/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/29/2023 | Approved | RAUL BARAJAS |
| Final | 1/19/2024 | Permit Finaled | RAUL BARAJAS |