9017 W 24TH ST 90034

Certificate Information: 9017 W 24TH ST 90034

Application / Permit
19016-20000-41321
Plan Check / Job No.
B19VN22676
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) (16'-11" X 18'-4") DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 9/10/2020
Issuing Office
Current Status
CofO Issued on 6/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 12/31/2019 RAPHAEL ROSAS
Corrections Issued 12/31/2019 RAPHAEL ROSAS
Building Plans Picked Up 1/9/2020 APPLICANT
Applicant returned to address corrections 6/16/2020 JASON JANGADA
Plan Check Approved 9/2/2020 RAPHAEL ROSAS
Issued 9/10/2020 APPLICANT
CofO in Progress 6/1/2021 EVAN COOPER
Permit Finaled 6/15/2021 VINCENT COTTON
CofO Issued 6/15/2021 VINCENT COTTON
Permit Finaled 6/15/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 1/17/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/17/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 1/17/2020 GUILLERMO PETRA
Sewer availability Cleared 1/17/2020 GUILLERMO PETRA
Construction near power lines Cleared 5/17/2020 RIDWAN HARDY
Grading Pre-Inspection Cleared 5/21/2020 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2020 Partial Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 10/21/2020 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 10/21/2020 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 10/21/2020 Approved KEVIN SARGSYAN
Green Building Rough 10/21/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 10/21/2020 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 10/27/2020 Corrections Issued KEVIN SARGSYAN
Green Building Rough 10/27/2020 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 10/27/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 11/5/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 11/5/2020 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 11/16/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/16/2020 Approved KEVIN SARGSYAN
Green Building Rough 11/16/2020 Approved KEVIN SARGSYAN
HVAC-Rough 11/16/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 11/16/2020 Partial Approval KEVIN SARGSYAN
Insulation 11/18/2020 Approved KEVIN SARGSYAN
Drywall Nailing 12/7/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 12/31/2020 Approved KEVIN SARGSYAN
Sewer 2/9/2021 Corrections Issued KEVIN SARGSYAN
Sewer 2/12/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/21/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Final 4/21/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 4/21/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 5/17/2021 Not Ready for Inspection KEVIN SARGSYAN
Final 5/17/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 5/17/2021 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 5/17/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 5/17/2021 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/17/2021 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 5/17/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 5/26/2021 Approved KEVIN SARGSYAN
Final 5/26/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 5/26/2021 Approved KEVIN SARGSYAN
HVAC-Final 5/26/2021 Approved KEVIN SARGSYAN
PLUMBING-Final 5/26/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 5/26/2021 Approved KEVIN SARGSYAN
Final 6/1/2021 OK to Issue CofO EVAN COOPER