3001-3003 S CARTER AVE 90292
Certificate Information: 3001-3003 S CARTER AVE 90292
- Application / Permit
- 19016-20000-41304
- Plan Check / Job No.
- B19VN22656
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- INTERIOR REMODEL TO (E) SFD AND CONVERT (E) 19'-10"x 10'-6" ATT. ONE CAR GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER LA SD WFPP.
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- Current Status
- CofO Issued on 4/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2019 | TROY DEGUZMAN |
| Corrections Issued | 12/30/2019 | TROY DEGUZMAN |
| Building Plans Picked Up | 1/3/2020 | APPLICANT |
| Applicant returned to address corrections | 7/2/2020 | TROY DEGUZMAN |
| Plan Check Approved | 7/7/2020 | TROY DEGUZMAN |
| Issued | 7/7/2020 | APPLICANT |
| CofO in Progress | 3/16/2021 | ENRIQUE MIRELES |
| CofO Issued | 4/6/2021 | VINCENT COTTON |
| Permit Finaled | 4/6/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Coastal Zone | Cleared | 5/7/2020 | PABLO ESTRADA |
| Miscellaneous | Cleared | 5/7/2020 | PABLO ESTRADA |
| Address approval | Cleared | 5/27/2020 | HISASHI KOBAYAKAWA |
| Address approval | Cleared | 5/27/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 5/27/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/27/2020 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2020 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 6/30/2020 | IRA BROWN |
| Specific Plan | Cleared | 6/30/2020 | IRA BROWN |
Contact Information
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD #280 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/4/2020 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 10/6/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/6/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/6/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/9/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 10/9/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/22/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/22/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/10/2020 | Approved | ENRIQUE MIRELES |
| Final | 1/7/2021 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/7/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/7/2021 | Approved | ENRIQUE MIRELES |
| Final | 1/11/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 1/14/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 2/24/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 3/16/2021 | OK to Issue CofO | ENRIQUE MIRELES |