451 N FLORES ST 90048

Certificate Information: 451 N FLORES ST 90048

Application / Permit
19016-20000-41300
Plan Check / Job No.
B19VN22650
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 18'1"x 18'1" GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 2/21/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 12/30/2019 LUIS RINCON
Corrections Issued 12/30/2019 LUIS RINCON
Building Plans Picked Up 1/2/2020 APPLICANT
Plan Check Approved 2/19/2020 LUIS RINCON
Issued 2/21/2020 LADBS
CofO in Progress 10/22/2020 CHRIS CHRISTENSEN
Permit Finaled 10/26/2020 DEROLD HAUFF
CofO Issued 10/26/2020 DEROLD HAUFF
Permit Finaled 10/26/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/28/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/28/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 1/28/2020 GUILLERMO PETRA
Sewer availability Cleared 1/28/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/26/2020 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 2/26/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 2/26/2020 Not Ready for Inspection RAUL BARAJAS
Shower Pan 2/26/2020 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/1/2020 Approved ROBERT CORNELL
Special/Order Compliance 4/1/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 4/10/2020 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/24/2020 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/24/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/24/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/28/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/28/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 4/28/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 4/28/2020 Approved CHRIS CHRISTENSEN
METHANE-Rough 4/28/2020 Approved CHRIS CHRISTENSEN
Enclosure/Fence 4/30/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/30/2020 Approved CHRIS CHRISTENSEN
Shower Pan 4/30/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 5/4/2020 Approved THOMAS LOGRASSO
Green Building Rough 5/4/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/4/2020 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 5/29/2020 Approved CHRIS CHRISTENSEN
Final 5/29/2020 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/29/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/29/2020 Approved CHRIS CHRISTENSEN
Final 6/9/2020 Conditional Approval CHRIS CHRISTENSEN