212 N JOY ST 90042
Certificate Information: 212 N JOY ST 90042
- Application / Permit
- 19016-20000-41211
- Plan Check / Job No.
- B19VN22580
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO ENLARGE BEDROOM, AND ADD ONE FULL BATHROOM AND ONE HALF BATHROOM & KITCHEN REMODEL. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/4/2020
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 12/27/2019 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/4/2020 | JENNIFER LEE |
| Issued | 2/5/2020 | LADBS |
| Permit Finaled | 5/4/2020 | OSVALDO PARAMO |
Permit Application Clearance Information
| HPOZ | Cleared | 2/3/2020 | KATIE DEBIASE |
| ZI | Cleared | 2/3/2020 | KATIE DEBIASE |
| Grading Pre-Inspection | Cleared | 2/4/2020 | BARTON HOLMES |
Contact Information
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/12/2020 | No Result Entered | ELMER BLAND |
| PLUMBING-Rough | 2/12/2020 | No Result Entered | ELMER BLAND |
| Footing/Foundation/Slab | 2/18/2020 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 2/18/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/20/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 2/20/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 2/20/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 2/20/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/24/2020 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/28/2020 | Conditional Approval | OSVALDO PARAMO |
| Insulation | 3/3/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 3/9/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 3/16/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/19/2020 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 3/19/2020 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 3/19/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 3/31/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 5/1/2020 | Corrections Issued | OSVALDO PARAMO |
| Final | 5/4/2020 | Permit Finaled | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/4/2020 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/4/2020 | Approved | OSVALDO PARAMO |