15705 1/2 W VANOWEN ST 91406

Certificate Information: 15705 1/2 W VANOWEN ST 91406

Application / Permit
19016-20000-40989
Plan Check / Job No.
B19VN22411
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant - Take Out
Work Description
CHANGE OF USE FROM DRY CLEANER TO TAKE OUT RESTAURANT(ICE CREAM SHOP) .
Permit Issued
Issued on 8/2/2021
Issuing Office
Current Status
CofO Issued on 5/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/8/2020 PINANK PATEL
Corrections Issued 1/22/2020 PINANK PATEL
Quality Review Completed 1/27/2020 ABDUL CHEGENI
Disabled Access Plans Picked Up 3/3/2020 APPLICANT
Applicant returned to address corrections 12/4/2020 PINANK PATEL
Applicant returned to address corrections 6/7/2021 PINANK PATEL
Plan Check Approved 7/30/2021 PINANK PATEL
Issued 8/2/2021 APPLICANT
Building Plans Picked Up 8/4/2021 APPLICANT
CofO in Progress 4/7/2022 CAMERON CHABAN
Permit Finaled 5/25/2022 RICKEY JACKSON
CofO Issued 5/25/2022 RICKEY JACKSON
Permit Finaled 5/25/2022 RICKEY JACKSON

Permit Application Clearance Information

Hold Cleared 1/13/2020 LOURDES RAMIRO
Comm Cor/Mini-Mall Cleared 2/21/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 2/21/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/21/2020 APEKSHYA BAJRACHARYA
ZA Case Cleared 2/21/2020 MIGUEL GAMBOA
Food establishment approval Cleared 9/9/2020 LACDHS APPROVED
DAS Clearance Cleared 1/28/2021 PINANK PATEL
Food Service Establishment Cleared 2/17/2021 JASH PATEL
Comm Cor/Mini-Mall Cleared 7/23/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2021 Corrections Issued DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 10/15/2021 Not Ready for Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 10/18/2021 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 12/10/2021 Not Ready for Inspection ANDREW DORSO
Wood Frame 2/1/2022 Partial Inspection DANIEL VARNUM
Wood Frame 2/24/2022 Approved CAMERON CHABAN
Final 3/22/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 3/22/2022 Approved CAMERON CHABAN
Final 4/6/2022 OK to Issue CofO CAMERON CHABAN