5937-5939 N WILKINSON AVE 91607

Certificate Information: 5937-5939 N WILKINSON AVE 91607

Application / Permit
19016-20000-40882
Plan Check / Job No.
B19VN22339
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20'-1" X 21'-2" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER WFPP.
Permit Issued
Issued on 1/31/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 JENNIFER LEE
Corrections Issued 12/27/2019 JENNIFER LEE
Building Plans Picked Up 12/30/2019 APPLICANT
Plan Check Approved 1/22/2020 JENNIFER LEE
Issued 1/31/2020 LADBS
CofO in Progress 4/19/2021 RICHARD DOCKUS
CofO Issued 5/22/2021 MICHAEL SMITH
Permit Finaled 5/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/22/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/22/2020 ADRIAN CASTRO
Sewer availability Cleared 1/22/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/15/2020 Partial Approval BRENDAN LOONEY
Underground Mechanical 7/15/2020 Approved BRENDAN LOONEY
Sewer 7/21/2020 Approved BRENDAN LOONEY
Footing/Foundation/Slab 7/22/2020 Approved BRENDAN LOONEY
ELECTRICAL-Rough 8/26/2020 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/26/2020 Not Ready for Inspection BRENDAN LOONEY
Shower Pan 8/26/2020 Approved BRENDAN LOONEY
Wood Frame 8/26/2020 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 8/31/2020 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 8/31/2020 Approved BRENDAN LOONEY
Wood Frame 8/31/2020 Partial Approval BRENDAN LOONEY
Wood Frame 9/10/2020 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 11/6/2020 Approved BRENDAN LOONEY
Drywall Nailing 11/6/2020 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Approved BRENDAN LOONEY
Green Building Rough 11/6/2020 Approved BRENDAN LOONEY
Wood Frame 11/6/2020 Approved BRENDAN LOONEY
Drywall Nailing 11/16/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/16/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 2/8/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 2/8/2021 Not Ready for Inspection ARAM AVEDISIAN
Green Building Final 2/8/2021 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Final 2/8/2021 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 2/8/2021 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 2/8/2021 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 2/8/2021 Approved ARAM AVEDISIAN
Final 2/17/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 2/17/2021 Approved BRENDAN LOONEY
PLUMBING-Final 2/17/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 2/17/2021 SGSOV Not Ready BRENDAN LOONEY
ELECTRICAL-Final 3/1/2021 Not Ready for Inspection JOHN HAYES
Final 3/1/2021 Corrections Issued JOHN HAYES
HVAC-Final 3/1/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/1/2021 SGSOV Not Ready JOHN HAYES
ELECTRICAL-Final 4/9/2021 Corrections Issued RICHARD DOCKUS
Final 4/9/2021 Corrections Issued RICHARD DOCKUS
HVAC-Final 4/9/2021 Approved RICHARD DOCKUS
PLUMBING-Final 4/9/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved RICHARD DOCKUS
ELECTRICAL-Final 4/16/2021 Approved RICHARD DOCKUS
Final 4/16/2021 OK to Issue CofO RICHARD DOCKUS
PLUMBING-Final 4/16/2021 Approved RICHARD DOCKUS
Service/Power Release 4/16/2021 Approved RICHARD DOCKUS