14033 W HARTSOOK ST 91423
Certificate Information: 14033 W HARTSOOK ST 91423
- Application / Permit
- 19016-20000-40801
- Plan Check / Job No.
- B19VN22250
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REPLACE SLAB OF 18'-9" X 20'-2" DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2020 | JENNIFER LEE |
| Corrections Issued | 1/6/2020 | JENNIFER LEE |
| Plan Check Approved | 1/21/2020 | ALDOUS CHIC |
| Issued | 2/5/2020 | LADBS |
| CofO in Progress | 8/1/2020 | CHARLES POWELL |
| CofO Issued | 2/20/2021 | MICHAEL SMITH |
| Permit Finaled | 2/20/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2020 | CHRISTINE REUSCH |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2020 | CHRISTINE REUSCH |
| Sewer availability | Cleared | 1/6/2020 | CHRISTINE REUSCH |
Contact Information
| Contractor | Pch Construction; Lic. No.: 1005176-B | 22107 AVENUE SAN LUIS WOODLAND HILLS, CA 91364 |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Corrections Issued | DANIEL ORRANTE |
| Footing/Foundation/Slab | 4/7/2020 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 5/5/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 5/5/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/5/2020 | Partial Inspection | MATTHEW NELSON |
| Wood Frame | 5/5/2020 | Approved | MATTHEW NELSON |
| Insulation | 5/28/2020 | Corrections Issued | CHARLES POWELL |
| Interior/Exterior Lathing | 5/28/2020 | Partial Approval | CHARLES POWELL |
| Shower Pan | 5/28/2020 | Approved | CHARLES POWELL |
| Insulation | 6/2/2020 | Partial Approval | CHARLES POWELL |
| Interior/Exterior Lathing | 6/9/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 6/23/2020 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 6/23/2020 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/21/2020 | Approved | CHARLES POWELL |
| Wood Frame | 7/21/2020 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/22/2020 | No Access for Inspection | JOHN HAYES |
| Drywall Nailing | 7/22/2020 | No Access for Inspection | JOHN HAYES |
| Final | 7/22/2020 | No Access for Inspection | JOHN HAYES |
| Green Building Final | 7/22/2020 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/22/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 7/22/2020 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/29/2020 | Corrections Issued | MATTHEW NELSON |
| Drywall Nailing | 7/29/2020 | Corrections Issued | MATTHEW NELSON |
| Final | 7/29/2020 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 7/29/2020 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/29/2020 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 7/29/2020 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/31/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 7/31/2020 | Approved | CHARLES POWELL |
| Final | 7/31/2020 | OK to Issue CofO | CHARLES POWELL |
| Green Building Final | 7/31/2020 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 7/31/2020 | SGSOV Approved | CHARLES POWELL |
| Smoke Detectors | 7/31/2020 | Approved | CHARLES POWELL |