1209 1/2 W 52ND ST 90037
Certificate Information: 1209 1/2 W 52ND ST 90037
- Application / Permit
- 19016-20000-40692
- Plan Check / Job No.
- B19VN22160
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED (E)GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2019 | ALDOUS CHIC |
| Corrections Issued | 1/13/2020 | ALDOUS CHIC |
| Plan Check Approved | 1/13/2020 | SARKIS HARABEDIAN |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 10/28/2020 | ROBERT MCDOWELL |
| Permit Finaled | 11/3/2020 | DEROLD HAUFF |
| CofO Issued | 11/3/2020 | DEROLD HAUFF |
| Permit Finaled | 11/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/20/2019 | GUILLERMO PETRA |
| ZI | Cleared | 12/20/2019 | NELSON RODRIGUEZ |
| Permit | Cleared | 1/7/2020 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 1/13/2020 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 3/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Wood Frame | 3/20/2020 | Partial Approval | ROBERT MCDOWELL |
| Wood Frame | 4/15/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 4/22/2020 | Approved | ROBERT MCDOWELL |
| Wood Frame | 4/22/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 4/29/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/20/2020 | Approved | SABAS ALONSO |
| Final | 7/17/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 7/17/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 7/17/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Smoke Detectors | 7/17/2020 | Approved | ROBERT MCDOWELL |
| Final | 7/30/2020 | Conditional Approval | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 7/30/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Final | 10/28/2020 | OK to Issue CofO | ROBERT MCDOWELL |