6329 1/2 W DREXEL AVE 90048
Certificate Information: 6329 1/2 W DREXEL AVE 90048
- Application / Permit
- 19016-20000-40689
- Plan Check / Job No.
- B19VN22159
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO ADU PER AB 494 AND SB 229
- Permit Issued
- Issued on 6/15/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | LAURA DUONG |
| Corrections Issued | 1/24/2020 | LAURA DUONG |
| Quality Review Completed | 1/27/2020 | KEN GILL |
| Building Plans Picked Up | 7/13/2021 | APPLICANT |
| Applicant returned to address corrections | 7/27/2021 | LAURA DUONG |
| Plan Check Approved | 8/6/2021 | LAURA DUONG |
| Plan Check Approved | 11/14/2022 | LAURA DUONG |
| Issued | 6/15/2023 | APPLICANT |
| CofO in Progress | 4/9/2025 | EVAN COOPER |
| Permit Finaled | 4/17/2025 | KENNETH NAGLE |
| CofO Issued | 4/17/2025 | KENNETH NAGLE |
| Permit Finaled | 4/17/2025 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 5/12/2020 | JUAN ASHTON |
| Construction near power lines | Cleared | 6/16/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/16/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | RENZ SORIANO |
| Tenant Habitability Plan | Cleared | 4/15/2021 | PHILLIP MUNGUIA |
| Green Code | Cleared | 5/27/2021 | LAURA DUONG |
Contact Information
| Contractor | Elite Building Concepts Inc; Lic. No.: 998829-B | 3345 DITCH RD SIMI VALLEY, CA 93063 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2023 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 8/28/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/30/2024 | Partial Inspection | HENRY KIM |
| Footing/Foundation/Slab | 4/2/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 5/2/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 5/2/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/2/2024 | Approved | MEL KHACHATOURIAN |
| Sewer | 5/2/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 5/16/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 5/16/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 5/20/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 5/22/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 5/30/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/4/2024 | Approved | ARAM AVEDISIAN |
| Final | 9/4/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 9/4/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/4/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/13/2025 | Approved | EVAN COOPER |
| Final | 3/13/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 3/13/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/13/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 3/21/2025 | Approved | EVAN COOPER |
| Final | 3/21/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 3/21/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/21/2025 | Approved | EVAN COOPER |
| Final | 4/9/2025 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 4/9/2025 | Approved | EVAN COOPER |