10624 N WOODWARD AVE 91040
Certificate Information: 10624 N WOODWARD AVE 91040
- Application / Permit
- 19016-20000-40362
- Plan Check / Job No.
- B19VN21941
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | ALDOUS CHIC |
| Corrections Issued | 12/18/2019 | ALDOUS CHIC |
| Plan Check Approved | 1/10/2020 | JEFFREY TANGONAN |
| Issued | 1/16/2020 | LADBS |
| CofO in Progress | 3/4/2021 | MATTHEW NELSON |
| CofO Issued | 5/18/2021 | MICHAEL SMITH |
| Permit Finaled | 5/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/23/2019 | GUILLERMO PETRA |
| Demolition Pre-Inspection | Cleared | 1/9/2020 | ALDOUS CHIC |
| Grading Pre-Inspection | Cleared | 1/10/2020 | BARTON HOLMES |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: C24587 | 21243 VENTURA BLVD #115 WOODLAND HILLS, CA 91364 |
| Contractor | Tavitian Martin Claudio; Lic. No.: 1017758-B | 5952 LUBAO AVENUE WOODLAND HILLS, CA 91367 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/30/2020 | Approved | MATTHEW NELSON |
| Pre-Inspection | 1/31/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/10/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/10/2020 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/27/2020 | Partial Inspection | MATTHEW NELSON |
| Green Building Rough | 3/27/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/16/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/16/2020 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/17/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 6/17/2020 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 6/17/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Sewer | 6/17/2020 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 6/17/2020 | Approved | PIERRE VEGA |
| ELECTRICAL-Rough | 6/19/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/19/2020 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 6/19/2020 | Approved | MATTHEW NELSON |
| Insulation | 6/26/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/6/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/6/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/9/2020 | Approved | MATTHEW NELSON |
| Final | 11/9/2020 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 11/9/2020 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 11/9/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/4/2021 | Approved | MATTHEW NELSON |
| Final | 3/4/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 3/4/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 3/4/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/4/2021 | Approved | MATTHEW NELSON |