14461 W PARTHENIA ST 91402

Certificate Information: 14461 W PARTHENIA ST 91402

Application / Permit
19016-20000-40333
Plan Check / Job No.
B19VN21930
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert the (e) detached garage into an Accessory Dwelling Unit per AB 494 and SB 229. All work done per WFPP.
Permit Issued
Issued on 2/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 ANGELICA DAVE
Corrections Issued 12/18/2019 ANGELICA DAVE
Plan Check Approved 1/29/2020 LUIS RINCON
Issued 2/11/2020 LADBS
CofO in Progress 6/22/2020 WILLIAM KUEHN
Permit Finaled 9/15/2020 MICHAEL SMITH
CofO Issued 9/15/2020 MICHAEL SMITH
Permit Finaled 9/15/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/18/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/18/2019 ADRIAN CASTRO
Sewer availability Cleared 12/18/2019 ADRIAN CASTRO
Construction near power lines Cleared 1/29/2020 RIDWAN HARDY

Contact Information

No Data Available.

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/23/2020 Conditional Approval WILLIAM KUEHN
Excavation/Setback/Form/Re-Bar 3/24/2020 Approved WILLIAM KUEHN
Underground Mechanical 3/24/2020 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 4/3/2020 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 4/3/2020 Partial Inspection BRENDAN LOONEY
Green Building Rough 4/3/2020 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 4/3/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 4/3/2020 Partial Approval BRENDAN LOONEY
Insulation 4/7/2020 Corrections Issued WILLIAM KUEHN
Special/Order Compliance 4/7/2020 Approved GREGG CUMMINGS
Insulation 4/10/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 4/10/2020 Partial Inspection WILLIAM KUEHN
Drywall Nailing 4/14/2020 Approved WILLIAM KUEHN
Underground Mechanical 5/27/2020 Approved PIERRE VEGA
BUILDING-Rough-Frame 5/29/2020 Not Ready for Inspection JOHN HAYES
Final 5/29/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 5/29/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 5/29/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 5/29/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/3/2020 Approved WILLIAM KUEHN
Final 6/3/2020 Not Ready for Inspection WILLIAM KUEHN
Green Building Final 6/3/2020 Approved WILLIAM KUEHN
Green Building Rough 6/3/2020 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 6/3/2020 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 6/3/2020 Approved WILLIAM KUEHN
Final 6/17/2020 Corrections Issued WILLIAM KUEHN
Final 6/19/2020 OK to Issue CofO WILLIAM KUEHN