1638 S ELECTRIC AVE 90291
Certificate Information: 1638 S ELECTRIC AVE 90291
- Application / Permit
- 19016-20000-40238
- Plan Check / Job No.
- B19VN21864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 23'-0"X 19-6" (E) GARAGE & STORAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEER. Comply with Code Enforcement Order issued 07/25/2019.
- Permit Issued
- Issued on 8/16/2021
- Issuing Office
- Current Status
- CofO Issued on 1/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | PARISA ZAHABI |
| Corrections Issued | 1/13/2020 | PARISA ZAHABI |
| Quality Review Completed | 1/27/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/10/2020 | PARISA ZAHABI |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Applicant returned to address corrections | 2/8/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 4/7/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 4/9/2021 | APPLICANT |
| Plan Check Approved | 8/16/2021 | JON BLAINE |
| Issued | 8/16/2021 | APPLICANT |
| CofO in Progress | 12/29/2021 | DAVID FEILER |
| Permit Finaled | 1/4/2022 | DANIEL ORRANTE |
| CofO Issued | 1/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 2/2/2021 | DAVID MATSON |
| Address approval | Cleared | 2/8/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/8/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/8/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2021 | ANTHONY MAINEZ |
| Construction within easement | Cleared | 3/1/2021 | RIDWAN HARDY |
| Coastal Zone | Cleared | 3/31/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 3/31/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 3/31/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 3/31/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 3/31/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 3/31/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 4/8/2021 | KURT CORRAL |
Contact Information
| Architect | Addison,, Susan L; Lic. No.: C25809 | 3456 ASHWOOD AVENUE LOS ANGELES, CA 90066 |
| Contractor | Carter Design & Remodeling Inc; Lic. No.: 932102-B | 23890 COPPERHILL DRIVE #375 VALENCIA, CA 91354 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2021 | No Access for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 8/26/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/8/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/8/2021 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 9/8/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 9/8/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/14/2021 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 9/14/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/14/2021 | Approved | JOHNNY MIRANDA |
| Insulation | 9/20/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/20/2021 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 9/27/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 9/27/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 10/20/2021 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 10/26/2021 | Approved | JOHN KAYON |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | DAVID FEILER |
| Final | 11/18/2021 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 11/18/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 11/24/2021 | Partial Approval | DAVID FEILER |
| Grounding or Bonding | 11/24/2021 | Partial Approval | DAVID FEILER |
| HVAC-Final | 11/24/2021 | Approved | DAVID FEILER |
| PLUMBING-Final | 11/24/2021 | Partial Approval | DAVID FEILER |
| Service/Power Release | 11/24/2021 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Final | 12/29/2021 | Approved | DAVID FEILER |
| Final | 12/29/2021 | OK to Issue CofO | DAVID FEILER |
| PLUMBING-Final | 12/29/2021 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 12/29/2021 | SGSOV Approved | DAVID FEILER |