7110 N KILTY AVE 91307
Certificate Information: 7110 N KILTY AVE 91307
- Application / Permit
- 19016-20000-40186
- Plan Check / Job No.
- B19VN21828
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | JEFFREY TANGONAN |
| Corrections Issued | 12/18/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 12/20/2019 | APPLICANT |
| Issued | 1/8/2020 | LADBS |
| CofO in Progress | 11/13/2020 | DAVID STEPANYAN |
| Permit Finaled | 11/18/2020 | JOHN JANSON |
| CofO Issued | 11/18/2020 | JOHN JANSON |
| Permit Finaled | 11/18/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/26/2019 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 1/8/2020 | JEFFREY TANGONAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/22/2020 | Partial Approval | DAVID STEPANYAN |
| Deputy Drilled-In Anchors | 6/23/2020 | Conditional Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 6/25/2020 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Insulation | 7/7/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/9/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 7/9/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Wood Frame | 7/9/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 7/21/2020 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 7/21/2020 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 7/24/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 7/24/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/31/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 7/31/2020 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 7/31/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 7/31/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 7/31/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 8/24/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 8/24/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 8/24/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 8/24/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 8/24/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 8/24/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 8/24/2020 | Approved | DAVID STEPANYAN |
| Insulation | 8/27/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 9/3/2020 | Approved | DAVID STEPANYAN |
| Gas Test | 10/2/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/2/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Final | 10/19/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 10/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Final | 10/19/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 10/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 10/19/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 10/19/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 10/19/2020 | SGSOV Approved | DAVID STEPANYAN |
| Service/Power Release | 10/19/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Smoke Detectors | 10/19/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 10/29/2020 | Approved | BRENDAN LOONEY |
| Final | 10/29/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 10/29/2020 | Conditional Approval | BRENDAN LOONEY |
| Service/Power Release | 10/29/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 11/13/2020 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 11/13/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 11/13/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 11/13/2020 | Approved | DAVID STEPANYAN |
| Service/Power Release | 11/13/2020 | Approved | DAVID STEPANYAN |