12808 W WADDELL ST 91607
Certificate Information: 12808 W WADDELL ST 91607
- Application / Permit
- 19016-20000-40169
- Plan Check / Job No.
- B19VN21818
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 6/10/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 12/17/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Plan Check Approved | 4/30/2020 | JEROME MAGAT PALMA |
| Issued | 6/10/2020 | LADBS |
| CofO in Progress | 1/25/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
| CofO Issued | 2/5/2022 | MICHAEL SMITH |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/19/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 3/28/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/28/2020 | RIDWAN HARDY |
Contact Information
| Architect | Sturgill,, Ben Curtis; Lic. No.: C23174 | 314 E BROADWAY # E GLENDALE, CA 91205 |
| Contractor | Owner-Builder | , |
| Engineer | O'Brien,, Kathleen Anne; Lic. No.: C49498 | 1058 PACIFIC AVE SIMI VALLEY, CA 93065 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 8/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 9/13/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 9/13/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/14/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/14/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Inspection | 10/14/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 11/5/2021 | Partial Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 11/5/2021 | Partial Inspection | MISAEL ESPARZA |
| Insulation | 11/9/2021 | Corrections Issued | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 11/9/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 11/12/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/17/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 12/3/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 12/10/2021 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/14/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 12/14/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 12/14/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/14/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/16/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 12/17/2021 | No Access for Inspection | THOMAS FINNILA |
| Insulation | 12/17/2021 | No Access for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/17/2021 | No Access for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 12/17/2021 | No Access for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/21/2021 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 12/21/2021 | Approved | JACK KARGODORIAN |
| Insulation | 12/21/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/21/2021 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 12/21/2021 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 12/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/23/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 12/30/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 12/30/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/30/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Final | 12/30/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 12/30/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/30/2021 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 1/6/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/6/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Green Building Final | 1/6/2022 | Approved | CHRISTOPHE COCHRAN |