- CONVERT (E) 18'-1"X20'-3" GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 4/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2019 | DAWN MC NULTY |
| Corrections Issued | 12/17/2019 | DAWN MC NULTY |
| Building Plans Picked Up | 12/18/2019 | APPLICANT |
| Plan Check Approved | 4/9/2020 | DAWN MC NULTY |
| Issued | 4/24/2020 | LADBS |
| CofO in Progress | 7/23/2020 | DANIEL DREW |
| Permit Finaled | 9/23/2020 | MICHAEL SMITH |
| CofO Issued | 9/23/2020 | MICHAEL SMITH |
| Permit Finaled | 9/23/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/26/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2019 | PAMELA TENEZA |
| Sewer availability | Cleared | 12/26/2019 | CELINA MORENO |
| ZI | Cleared | 12/26/2019 | ANNA VIDAL |
| Construction near power lines | Cleared | 2/27/2020 | ERNEST FRESQUEZ |
Contact Information
| Contractor | E H D Builders Inc; Lic. No.: 1034101-B | 18375 VENTURA BLVD 122 TARZANA, CA 91356 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/28/2020 | Approved | DANIEL ORRANTE |
| Footing/Foundation/Slab | 4/28/2020 | Approved | DANIEL ORRANTE |
| Sewer | 4/28/2020 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 5/14/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 5/14/2020 | Partial Inspection | WILLIAM KUEHN |
| HVAC-Rough | 5/14/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 5/14/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2020 | Partial Approval | THOMAS FINNILA |
| Insulation | 5/18/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 5/20/2020 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/20/2020 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 5/20/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/28/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 7/10/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 7/10/2020 | Corrections Issued | DANIEL DREW |
| Final | 7/10/2020 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Final | 7/10/2020 | Approved | DANIEL DREW |
| PLUMBING-Final | 7/10/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 7/10/2020 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 7/10/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 7/20/2020 | Approved | MICHEL ABAJAN |
| Final | 7/20/2020 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 7/20/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/20/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/23/2020 | Approved | DANIEL DREW |
| Final | 7/23/2020 | OK to Issue CofO | DANIEL DREW |
| HVAC-Final | 7/23/2020 | Approved | DANIEL DREW |
| PLUMBING-Final | 7/23/2020 | Approved | DANIEL DREW |