2822 S MALCOLM AVE 90064
Certificate Information: 2822 S MALCOLM AVE 90064
- Application / Permit
- 19016-20000-39797
- Plan Check / Job No.
- B19VN21607
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NONSTRUCT REMODEL - CONVERT EX DETACHED REC RM W/ ATT GARAGE INTO ACCESSORY DWELLING UNIT W/ ATT GARAGE PER AB 494 AND SB 229. ALL WORK PER WFPP. THE EXISTING GARAGE TO SERVE EXISTING MAIN DWELLING. SEE COMMENTS.
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | HAYATO TSUCHIYA |
| Corrections Issued | 12/13/2019 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 12/13/2019 | APPLICANT |
| Applicant returned to address corrections | 5/22/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/27/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 9/23/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 11/12/2020 | HAYATO TSUCHIYA |
| Issued | 11/25/2020 | APPLICANT |
| CofO in Progress | 9/21/2021 | KENNETH NAGLE |
| Permit Finaled | 9/21/2021 | KENNETH NAGLE |
| CofO Issued | 9/21/2021 | KENNETH NAGLE |
| Permit Finaled | 9/21/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/26/2019 | JOHN LIN |
| Specific Plan | Cleared | 12/26/2019 | ALBERT ISAGULIAN |
| Construction near power lines | Cleared | 3/10/2020 | RIDWAN HARDY |
| Address approval | Cleared | 7/1/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | DINAH GARIN |
Contact Information
| Contractor | Dannick Design Inc; Lic. No.: 801686-B | 24730 AVENUE TIBBITS #160 VALENCIA, CA 91355 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/4/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Pre-Inspection | 2/4/2021 | Approved | RICHARD ROBLES |
| ELECTRICAL-Rough | 2/26/2021 | Corrections Issued | RICHARD ROBLES |
| PLUMBING-Rough | 2/26/2021 | Partial Approval | RICHARD ROBLES |
| ELECTRICAL-Rough | 3/9/2021 | Corrections Issued | RICHARD ROBLES |
| HVAC-Rough | 3/9/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Sewer | 3/9/2021 | Approved | RICHARD ROBLES |
| BUILDING-Rough-Frame | 3/12/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/12/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 3/12/2021 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 3/12/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 3/12/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/25/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/25/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 4/12/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 4/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 4/23/2021 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 4/29/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 4/29/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/29/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 4/29/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/5/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/5/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/28/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 6/28/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/28/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 6/28/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 6/28/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| MERV13>=Final | 6/28/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| MERV13>=Rough | 6/28/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 6/28/2021 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 6/28/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| Drywall Nailing | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| Final | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| Green Building Final | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| Green Building Rough | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| MERV13>=Final | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| MERV13>=Rough | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| Smoke Detectors | 8/18/2021 | No Access for Inspection | KENNETH NAGLE |
| Special/Order Compliance | 8/25/2021 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 8/27/2021 | Conditional Approval | EVAN COOPER |
| Drywall Nailing | 8/27/2021 | Approved | EVAN COOPER |
| Final | 8/27/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 8/27/2021 | Approved | EVAN COOPER |
| Green Building Rough | 8/27/2021 | Approved | EVAN COOPER |
| HVAC-Final | 8/27/2021 | Approved | EVAN COOPER |
| Insulation | 8/27/2021 | Approved | EVAN COOPER |
| MERV13>=Final | 8/27/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/27/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 8/27/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/21/2021 | Approved | KENNETH NAGLE |
| Final | 9/21/2021 | OK to Issue CofO | KENNETH NAGLE |
| MERV13>=Rough | 9/21/2021 | Approved | KENNETH NAGLE |