3333 S MANNING AVE 90064
Certificate Information: 3333 S MANNING AVE 90064
- Application / Permit
- 19016-20000-39587
- Plan Check / Job No.
- B19VN21475
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (10) Home for the Aged with special care
- Work Description
- TENANT IMPROVEMENT & INTERIOR REMODEL TO (E) BANQUET HALL ACCESSORY TO A HOME FOR THE AGED WITH SPECIAL CARE; RE-ROOF (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 6/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/28/2023
Permit Application Status History
| Submitted | 12/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/15/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/16/2020 | GUANG MIN TUNG |
| Green Plans Picked Up | 1/16/2020 | APPLICANT |
| Building Plans Picked Up | 1/17/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 1/28/2020 | APPLICANT |
| Plan Check Approved | 12/3/2020 | NILOOFAR MEHRAIN |
| Issued | 6/15/2021 | APPLICANT |
| Permit Finaled | 3/24/2023 | PAUL DAVIDSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2020 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 2/20/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 2/20/2020 | MARKOS PEREZ-BRAN |
| Public Works-Highway Ded. | Cleared | 2/20/2020 | MARKOS PEREZ-BRAN |
| Public Works-Open Permits | Cleared | 2/20/2020 | MARKOS PEREZ-BRAN |
| Public Works-Sewers | Cleared | 2/20/2020 | MARKOS PEREZ-BRAN |
| Specific Plan | Cleared | 2/27/2020 | DYLAN SITTIG |
| ZI | Cleared | 2/27/2020 | DYLAN SITTIG |
| Fire Marshall Fire Life Safety | Cleared | 2/28/2020 | VIDAL GARCIA |
| Green Code | Cleared | 3/3/2020 | AARON COSTA |
| DAS Clearance | Cleared | 6/17/2020 | OLLIE CARTER |
| Food Service Establishment | Cleared | 6/22/2020 | KENNETH BROWNE |
| ZA Case | Cleared | 10/15/2020 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 11/6/2020 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 11/9/2020 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 11/9/2020 | HERMINIGILDO AGUSTIN |
| Food establishment approval | Cleared | 12/2/2020 | LACDHS APPROVED |
Contact Information
| Architect | Pence,, Melisa Christine; Lic. No.: C29539 | 322 AMETHYST AVENUE NEWPORT BEACH, CA 92662 |
| Contractor | Hoffman & Associates Building Corporation; Lic. No.: 421531-B | 7120 HAYVENHURST AVE STE 110 VAN NUYS, CA 91406 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2021 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 1/26/2022 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 2/1/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 2/8/2022 | Partial Approval | TIMOTHY BUXTON |
| Green Building Rough | 3/11/2022 | Approved | PAUL DAVIDSON |
| Wood Frame | 3/11/2022 | Partial Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 4/20/2022 | Conditional Approval | PAUL DAVIDSON |
| Drywall Nailing | 4/26/2022 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 4/26/2022 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 5/11/2022 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 5/11/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 5/11/2022 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 5/13/2022 | Partial Approval | JOHN DODGE |
| Wood Frame | 5/24/2022 | Approved | PAUL DAVIDSON |
| Insulation | 5/31/2022 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 6/8/2022 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 7/5/2022 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 7/21/2022 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Partial Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV Not Ready | PAUL DAVIDSON |
| Final | 2/24/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Final | 2/24/2023 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 2/24/2023 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 3/24/2023 | Permit Finaled | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 3/24/2023 | Approved | PAUL DAVIDSON |