7449 N DE CELIS PL 91406

Certificate Information: 7449 N DE CELIS PL 91406

Application / Permit
19016-20000-39476
Plan Check / Job No.
B19VN21420
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18'-2" X 20'-1" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/16/2019 JENNIFER LEE
Corrections Issued 12/16/2019 JENNIFER LEE
Plan Check Approved 1/28/2020 ALDOUS CHIC
Issued 2/14/2020 LADBS
CofO in Progress 6/22/2020 MICHEL ABAJAN
Permit Finaled 7/20/2020 MICHAEL SMITH
CofO Issued 7/20/2020 MICHAEL SMITH
Permit Finaled 7/20/2020 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 1/4/2020 OSCAR CASTRO
Address approval Cleared 1/21/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/21/2020 THOMAS LANG
Permit Cleared 1/21/2020 THOMAS LANG
Sewer availability Cleared 1/21/2020 THOMAS LANG
Trees in Parkway Cleared 1/24/2020 JOHN KIM

Contact Information

Contractor Yaghoubi M Corp; Lic. No.: 972773-B 6459 LUBAO AVENUE      WOODLAND HILLS, CA 91367
Engineer Christenson,, Paul Scott; Lic. No.: C57182 3529 COASTVIEW CT      CARLSBAD, CA 92010

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2020 Corrections Issued ROBERT VORHIS
Pre-Inspection 2/22/2020 Corrections Issued ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Not Ready for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 3/2/2020 Approved JACK KARGODORIAN
Underground Mechanical 3/12/2020 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 3/19/2020 No Access for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 3/23/2020 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 3/23/2020 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 3/28/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 3/28/2020 Approved KATHRYN BUTTERWORTH
Insulation 3/28/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/2/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 4/2/2020 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 4/2/2020 Approved JENNIFER RABUCHIN
HVAC-Rough 4/2/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/2/2020 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 4/8/2020 Approved JENNIFER RABUCHIN
Shower Pan 4/8/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 4/9/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 6/2/2020 Approved MARK JOHNSON
Final 6/2/2020 Corrections Issued MARK JOHNSON
Green Building Final 6/2/2020 Approved MARK JOHNSON
HVAC-Final 6/2/2020 Approved MARK JOHNSON
PLUMBING-Final 6/2/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 6/2/2020 SGSOV Not Ready MARK JOHNSON
Service/Power Release 6/2/2020 Not Required MARK JOHNSON
Smoke Detectors 6/2/2020 Approved MARK JOHNSON
Final 6/22/2020 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 6/22/2020 Approved MICHEL ABAJAN